A heuristic job-shop scheduling algorithm to minimize the total holding cost of completed and in-process products subject to no tardy jobs

Meeting due dates is the most important goal of scheduling if the due date of each job has been promised to its customer. This paper considers the job-shop scheduling problem of minimizing the total holding cost of completed and in-process products subject to no tardy jobs. A heuristic algorithm bas...

Celý popis

Uloženo v:
Podrobná bibliografie
Vydáno v:International journal of production economics Ročník 101; číslo 1; s. 19 - 29
Hlavní autoři: Ohta, Hiroshi, Nakatani, Toshihiro
Médium: Journal Article
Jazyk:angličtina
Vydáno: Amsterdam Elsevier B.V 01.05.2006
Elsevier
Elsevier Sequoia S.A
Edice:International Journal of Production Economics
Témata:
ISSN:0925-5273, 1873-7579
On-line přístup:Získat plný text
Tagy: Přidat tag
Žádné tagy, Buďte první, kdo vytvoří štítek k tomuto záznamu!
Popis
Shrnutí:Meeting due dates is the most important goal of scheduling if the due date of each job has been promised to its customer. This paper considers the job-shop scheduling problem of minimizing the total holding cost of completed and in-process products subject to no tardy jobs. A heuristic algorithm based on the shifting bottleneck procedure is proposed for solving the minimum total holding cost problem subject to no tardy jobs. Several benchmark problems which are commonly used for job-shop scheduling problems of minimizing the makespan are solved by the proposed method and the results are reported.
Bibliografie:SourceType-Scholarly Journals-1
ObjectType-Feature-1
content type line 14
ISSN:0925-5273
1873-7579
DOI:10.1016/j.ijpe.2005.05.004