Complexity of single machine scheduling subject to nonnegative inventory constraints

This paper focuses on single machine scheduling subject to inventory constraints. Jobs either add items to an inventory or remove items from that inventory. Jobs that have to remove items cannot be processed if the required number of items is not available. We consider scheduling problems on a singl...

Celý popis

Uloženo v:
Podrobná bibliografie
Vydáno v:European journal of operational research Ročník 207; číslo 2; s. 605 - 619
Hlavní autoři: Briskorn, Dirk, Choi, Byung-Cheon, Lee, Kangbok, Leung, Joseph, Pinedo, Michael
Médium: Journal Article
Jazyk:angličtina
Vydáno: Amsterdam Elsevier B.V 01.12.2010
Elsevier
Elsevier Sequoia S.A
Edice:European Journal of Operational Research
Témata:
ISSN:0377-2217, 1872-6860
On-line přístup:Získat plný text
Tagy: Přidat tag
Žádné tagy, Buďte první, kdo vytvoří štítek k tomuto záznamu!
Abstract This paper focuses on single machine scheduling subject to inventory constraints. Jobs either add items to an inventory or remove items from that inventory. Jobs that have to remove items cannot be processed if the required number of items is not available. We consider scheduling problems on a single machine with the minimization of the total weighted completion time, the maximum lateness, and the number of tardy jobs, respectively, as objective and determine their computational complexity. Since the general versions of our problems turn out to be strongly NP-hard, we consider special cases by assuming that different jobs have certain parameter values in common. We determine the computational complexity for all special cases when the objective is either to minimize total completion time or to minimize maximum lateness and for several special cases when the objective is either to minimize total weighted completion time or to minimize the number of tardy jobs.
AbstractList This paper focuses on single machine scheduling subject to inventory constraints. Jobs either add items to an inventory or remove items from that inventory. Jobs that have to remove items cannot be processed if the required number of items is not available. We consider scheduling problems on a single machine with the minimization of the total weighted completion time, the maximum lateness, and the number of tardy jobs, respectively, as objective and determine their computational complexity. Since the general versions of our problems turn out to be strongly NP-hard, we consider special cases by assuming that different jobs have certain parameter values in common. We determine the computational complexity for all special cases when the objective is either to minimize total completion time or to minimize maximum lateness and for several special cases when the objective is either to minimize total weighted completion time or to minimize the number of tardy jobs.
This paper focuses on single machine scheduling subject to inventory constraints. Jobs either add items to an inventory or remove items from that inventory. Jobs that have to remove items cannot be processed if the required number of items is not available. We consider scheduling problems on a single machine with the minimization of the total weighted completion time, the maximum lateness, and the number of tardy jobs, respectively, as objective and determine their computational complexity. Since the general versions of our problems turn out to be strongly NP-hard, we consider special cases by assuming that different jobs have certain parameter values in common. We determine the computational complexity for all special cases when the objective is either to minimize total completion time or to minimize maximum lateness and for several special cases when the objective is either to minimize total weighted completion time or to minimize the number of tardy jobs. [PUBLICATION ABSTRACT]
Author Choi, Byung-Cheon
Pinedo, Michael
Leung, Joseph
Briskorn, Dirk
Lee, Kangbok
Author_xml – sequence: 1
  givenname: Dirk
  surname: Briskorn
  fullname: Briskorn, Dirk
  email: briskorn@wiso.uni-koeln.de
  organization: Universität zu Köln, Wirtschafts- und Sozialwissenschaftliche Fakultät, Albertus-Magnus-Platz, 50923 Köln, Germany
– sequence: 2
  givenname: Byung-Cheon
  surname: Choi
  fullname: Choi, Byung-Cheon
  email: polytime@cnu.ac.kr
  organization: Department of Business Administration, Chungnam National University, 79 Daehangno, Yuseong-gu, Daejeon 305-704, South Korea
– sequence: 3
  givenname: Kangbok
  surname: Lee
  fullname: Lee, Kangbok
  email: klee3@stern.nyu.edu
  organization: Stern School of Business, New York University, 44 West 4th Street, New York, NY 10012, USA
– sequence: 4
  givenname: Joseph
  surname: Leung
  fullname: Leung, Joseph
  email: leung@cis.njit.edu
  organization: Department of Computer Science, New Jersey Institute of Technology, University Heights, Newark, NJ 07102, USA
– sequence: 5
  givenname: Michael
  surname: Pinedo
  fullname: Pinedo, Michael
  email: mpinedo@stern.nyu.edu
  organization: Stern School of Business, New York University, 44 West 4th Street, New York, NY 10012, USA
BackLink http://www.econis.eu/PPNSET?PPN=635289539$$DView this record in ZBW - Deutsche Zentralbibliothek für Wirtschaftswissenschaften
http://pascal-francis.inist.fr/vibad/index.php?action=getRecordDetail&idt=23117427$$DView record in Pascal Francis
http://econpapers.repec.org/article/eeeejores/v_3a207_3ay_3a2010_3ai_3a2_3ap_3a605-619.htm$$DView record in RePEc
BookMark eNp9UsFq3DAQFSWFbtL-QC81hdKTt5K8kmzopSxtUhroJT0LWR5nZWzJlbRL9u87zi6h5BDBaIbhzczTPF2SCx88EPKe0TWjTH4Z1jCEuOYUE1SsaSVfkRWrFS9lLekFWdFKqZJzpt6Qy5QGSikTTKzI3TZM8wgPLh-L0BfJ-fsRisnYnfNQJLuDbj9iskj7dgCbixwKnO3h3mR3gML5A_gc4rGwwaccjfM5vSWvezMmeHf2V-TPj-9325vy9vf1z-2329IKxnPZKtZD1bZtpxhTlhmpmsbWFWOWbSg0olLNRklBjQQQvaSsq5F321La21b11RX5fOo7x_B3DynrySUL42g8hH3SSlLOaFM1iPz4DDmEffRITquNaATOUwj6dQJFmMHqObrJxKMGPLhcSPqgK8Opwvv4GDGKzi0h2owmqdCSNXqXJ-z26TzSJGvGPhpvXXrqyvGZasOXqR9OOMAN_geQleA17mAhz08IG0NKEfonDBJY5NeDXhjqR0ZIAeXHovpZkXUZNQt-EWl8ufTrmRFqd3AQdbIOvIXORfwCugvupfJ_t__Lqw
CODEN EJORDT
CitedBy_id crossref_primary_10_1057_jors_2012_155
crossref_primary_10_1007_s10951_012_0297_6
crossref_primary_10_1016_j_asoc_2020_106736
crossref_primary_10_1016_j_ejor_2020_03_029
crossref_primary_10_1007_s00453_025_01331_x
crossref_primary_10_1109_TASE_2018_2884618
crossref_primary_10_1007_s10472_019_09646_6
crossref_primary_10_1016_j_ejor_2014_03_012
crossref_primary_10_1016_j_ejor_2024_05_029
crossref_primary_10_1016_j_ejor_2015_01_003
crossref_primary_10_1080_00207543_2013_849825
crossref_primary_10_1002_nav_22256
crossref_primary_10_1007_s10588_017_9247_3
crossref_primary_10_1007_s10951_015_0455_8
crossref_primary_10_1016_j_cie_2017_01_023
crossref_primary_10_1016_j_omega_2021_102431
crossref_primary_10_1007_s00170_011_3180_2
crossref_primary_10_1007_s11740_020_01013_3
crossref_primary_10_1007_s00291_012_0311_6
crossref_primary_10_1007_s10951_012_0266_0
crossref_primary_10_1016_j_ejor_2016_09_007
crossref_primary_10_1002_cpe_6540
crossref_primary_10_1145_3178539
crossref_primary_10_1145_3450524
crossref_primary_10_1007_s10951_015_0433_1
crossref_primary_10_1016_j_cie_2022_108662
crossref_primary_10_1007_s10951_011_0261_x
crossref_primary_10_56809_icujtas_1512826
crossref_primary_10_1016_j_orl_2015_09_004
crossref_primary_10_1016_j_tcs_2014_11_007
crossref_primary_10_1007_s10479_015_1993_3
crossref_primary_10_1007_s10951_013_0346_9
crossref_primary_10_1016_j_ejor_2022_03_047
crossref_primary_10_1155_2018_8073648
crossref_primary_10_1016_j_cie_2012_02_006
crossref_primary_10_1016_j_ejor_2015_07_001
crossref_primary_10_1016_j_swevo_2022_101200
crossref_primary_10_1080_21681015_2019_1647300
crossref_primary_10_1016_j_ejor_2021_07_001
Cites_doi 10.1007/s001860200251
10.1016/S0377-2217(98)00017-4
10.1016/j.ejor.2004.04.019
10.1002/jos.91
10.1016/j.ejor.2004.04.018
10.1016/j.cie.2005.07.002
10.1007/s00291-005-0008-1
10.1145/77600.77615
10.1287/moor.17.1.36
10.1016/S0004-3702(02)00362-4
10.1016/j.ejor.2006.10.047
10.1145/322203.322213
10.1016/S0167-5060(08)70743-X
10.1007/s00291-003-0133-7
10.1007/s00291-008-0139-2
10.1007/s002910000042
10.1016/j.dam.2009.02.012
10.1016/j.ejor.2007.11.010
10.1002/nav.20095
ContentType Journal Article
Copyright 2010 Elsevier B.V.
2015 INIST-CNRS
Copyright Elsevier Sequoia S.A. Dec 1, 2010
Copyright_xml – notice: 2010 Elsevier B.V.
– notice: 2015 INIST-CNRS
– notice: Copyright Elsevier Sequoia S.A. Dec 1, 2010
DBID AAYXX
CITATION
OQ6
IQODW
DKI
X2L
7SC
7TB
8FD
FR3
JQ2
L7M
L~C
L~D
7TA
JG9
DOI 10.1016/j.ejor.2010.05.036
DatabaseName CrossRef
ECONIS
Pascal-Francis
RePEc IDEAS
RePEc
Computer and Information Systems Abstracts
Mechanical & Transportation Engineering Abstracts
Technology Research Database
Engineering Research Database
ProQuest Computer Science Collection
Advanced Technologies Database with Aerospace
Computer and Information Systems Abstracts – Academic
Computer and Information Systems Abstracts Professional
Materials Business File
Materials Research Database
DatabaseTitle CrossRef
Technology Research Database
Computer and Information Systems Abstracts – Academic
Mechanical & Transportation Engineering Abstracts
ProQuest Computer Science Collection
Computer and Information Systems Abstracts
Engineering Research Database
Advanced Technologies Database with Aerospace
Computer and Information Systems Abstracts Professional
Materials Research Database
Materials Business File
DatabaseTitleList Materials Research Database


Technology Research Database
DeliveryMethod fulltext_linktorsrc
Discipline Engineering
Computer Science
Business
Applied Sciences
EISSN 1872-6860
EndPage 619
ExternalDocumentID 2115432741
eeeejores_v_3a207_3ay_3a2010_3ai_3a2_3ap_3a605_619_htm
23117427
635289539
10_1016_j_ejor_2010_05_036
S0377221710003929
Genre Feature
GroupedDBID --K
--M
-~X
.DC
.~1
0R~
1B1
1OL
1RT
1~.
1~5
29G
4.4
41~
457
4G.
5GY
5VS
6OB
7-5
71M
8P~
9JN
9JO
AAAKF
AAAKG
AABNK
AACTN
AAEDT
AAEDW
AAIAV
AAIKJ
AAKOC
AALRI
AAOAW
AAQFI
AAQXK
AARIN
AAXUO
AAYFN
AAYOK
ABAOU
ABBOA
ABFNM
ABFRF
ABJNI
ABMAC
ABUCO
ABXDB
ABYKQ
ACAZW
ACDAQ
ACGFO
ACGFS
ACIWK
ACNCT
ACNNM
ACRLP
ACZNC
ADBBV
ADEZE
ADGUI
ADIYS
ADJOM
ADMUD
AEBSH
AEFWE
AEKER
AENEX
AFFNX
AFKWA
AFTJW
AGHFR
AGUBO
AGYEJ
AHHHB
AHZHX
AI.
AIALX
AIEXJ
AIGVJ
AIKHN
AITUG
AJBFU
AJOXV
ALMA_UNASSIGNED_HOLDINGS
AMFUW
AMRAJ
AOUOD
APLSM
ARUGR
ASPBG
AVWKF
AXJTR
AZFZN
BKOJK
BKOMP
BLXMC
CS3
DU5
EBS
EFJIC
EFLBG
EJD
EO8
EO9
EP2
EP3
F5P
FDB
FEDTE
FGOYB
FIRID
FNPLU
FYGXN
G-Q
GBLVA
GBOLZ
HAMUX
HVGLF
HZ~
IHE
J1W
KOM
LY1
M41
MHUIS
MO0
MS~
N9A
O-L
O9-
OAUVE
OZT
P-8
P-9
P2P
PC.
PQQKQ
Q38
R2-
RIG
ROL
RPZ
RXW
SCC
SDF
SDG
SDP
SDS
SES
SEW
SPC
SPCBC
SSB
SSD
SSV
SSW
SSZ
T5K
TAE
TN5
U5U
VH1
WUQ
XPP
ZMT
~02
~G-
9DU
AATTM
AAXKI
AAYWO
AAYXX
ABWVN
ACLOT
ACRPL
ACVFH
ADCNI
ADNMO
ADXHL
AEIPS
AEUPX
AFJKZ
AFPUW
AGQPQ
AIGII
AIIUN
AKBMS
AKRWK
AKYEP
ANKPU
APXCP
CITATION
EFKBS
~HD
OQ6
AFXIZ
AGCQF
AGRNS
BNPGV
IQODW
SSH
02
08R
0R
1
41
6XO
8P
AAPBV
ABFLS
ADALY
DKI
G-
HZ
IPNFZ
K
M
MS
PQEST
STF
X
X2L
7SC
7TB
8FD
FR3
JQ2
L7M
L~C
L~D
7TA
JG9
ID FETCH-LOGICAL-c512t-b71fe3bbbd7117c1a6799c8311c140e9537947650a6ee5f601d8001bb00fcb7f3
ISICitedReferencesCount 44
ISICitedReferencesURI http://www.webofscience.com/api/gateway?GWVersion=2&SrcApp=Summon&SrcAuth=ProQuest&DestLinkType=CitingArticles&DestApp=WOS_CPL&KeyUT=000281107200007&url=https%3A%2F%2Fcvtisr.summon.serialssolutions.com%2F%23%21%2Fsearch%3Fho%3Df%26include.ft.matches%3Dt%26l%3Dnull%26q%3D
ISSN 0377-2217
IngestDate Sun Nov 09 10:52:05 EST 2025
Mon Jul 14 10:06:01 EDT 2025
Wed Aug 18 03:50:56 EDT 2021
Mon Jul 21 09:11:39 EDT 2025
Sat Mar 08 16:22:31 EST 2025
Sat Nov 29 01:41:00 EST 2025
Tue Nov 18 21:07:20 EST 2025
Fri Feb 23 02:32:27 EST 2024
IsPeerReviewed true
IsScholarly true
Issue 2
Keywords Inventory constraints
Polynomial-time algorithms
Machine scheduling
Computational complexity
Strong NP-hardness
Minimization
Scheduling
Makespan
Polynomial method
Delay
Polynomial time
Production management
NP hard problem
Lateness
Single machine
Language English
License https://www.elsevier.com/tdm/userlicense/1.0
CC BY 4.0
LinkModel OpenURL
MergedId FETCHMERGED-LOGICAL-c512t-b71fe3bbbd7117c1a6799c8311c140e9537947650a6ee5f601d8001bb00fcb7f3
Notes SourceType-Scholarly Journals-1
ObjectType-Feature-1
content type line 14
ObjectType-Article-2
content type line 23
PQID 745951407
PQPubID 45678
PageCount 15
ParticipantIDs proquest_miscellaneous_760210939
proquest_journals_745951407
repec_primary_eeeejores_v_3a207_3ay_3a2010_3ai_3a2_3ap_3a605_619_htm
pascalfrancis_primary_23117427
econis_primary_635289539
crossref_primary_10_1016_j_ejor_2010_05_036
crossref_citationtrail_10_1016_j_ejor_2010_05_036
elsevier_sciencedirect_doi_10_1016_j_ejor_2010_05_036
PublicationCentury 2000
PublicationDate 2010-12-01
PublicationDateYYYYMMDD 2010-12-01
PublicationDate_xml – month: 12
  year: 2010
  text: 2010-12-01
  day: 01
PublicationDecade 2010
PublicationPlace Amsterdam
PublicationPlace_xml – name: Amsterdam
PublicationSeriesTitle European Journal of Operational Research
PublicationTitle European journal of operational research
PublicationYear 2010
Publisher Elsevier B.V
Elsevier
Elsevier Sequoia S.A
Publisher_xml – name: Elsevier B.V
– name: Elsevier
– name: Elsevier Sequoia S.A
References Neumann, Schwindt (bib14) 2002; 56
Ahuja, Mehlhorn, Orlin, Tarjan (bib1) 1990; 37
Brucker, Heitmann, Hurink (bib5) 2003; 25
Nowicki (bib16) 1999; 116
McWilliams, Stanfield, Geiger (bib13) 2005; 49
Grigoriev, Holthuijsen, Klundert (bib9) 2005; 52
Neumann, Schwindt, Trautmann (bib15) 2005; 165
Beck (bib3) 2002; 5
Boysen, Fliedner, Scholl (bib4) 2010; 32
Graham, Lawler, Lenstra, Rinnooy Kan (bib8) 1979; 5
Sourd, Rogerie (bib19) 2005; 165
Carlier, Moukrim, Xu (bib7) 2009; 157
Lenstra, Rinnooy Kan, Brucker (bib12) 1977; 1
Papadimitriou, Kanellakis (bib17) 1980; 27
Bartels, Zimmermann (bib2) 2009; 193
Brucker, Heitmann, Hurink, Nieberg (bib6) 2006; 28
Laborie (bib11) 2003; 143
Hassin (bib10) 1992; 17
Yu, Egbelu (bib20) 2008; 184
Schwindt, Trautmann (bib18) 2000; 22
Beck (10.1016/j.ejor.2010.05.036_bib3) 2002; 5
Grigoriev (10.1016/j.ejor.2010.05.036_bib9) 2005; 52
Yu (10.1016/j.ejor.2010.05.036_bib20) 2008; 184
Brucker (10.1016/j.ejor.2010.05.036_bib5) 2003; 25
Boysen (10.1016/j.ejor.2010.05.036_bib4) 2010; 32
Brucker (10.1016/j.ejor.2010.05.036_bib6) 2006; 28
Neumann (10.1016/j.ejor.2010.05.036_bib14) 2002; 56
McWilliams (10.1016/j.ejor.2010.05.036_bib13) 2005; 49
Hassin (10.1016/j.ejor.2010.05.036_bib10) 1992; 17
Bartels (10.1016/j.ejor.2010.05.036_bib2) 2009; 193
Laborie (10.1016/j.ejor.2010.05.036_bib11) 2003; 143
Papadimitriou (10.1016/j.ejor.2010.05.036_bib17) 1980; 27
Nowicki (10.1016/j.ejor.2010.05.036_bib16) 1999; 116
Carlier (10.1016/j.ejor.2010.05.036_bib7) 2009; 157
Schwindt (10.1016/j.ejor.2010.05.036_bib18) 2000; 22
Ahuja (10.1016/j.ejor.2010.05.036_bib1) 1990; 37
Graham (10.1016/j.ejor.2010.05.036_bib8) 1979; 5
Lenstra (10.1016/j.ejor.2010.05.036_bib12) 1977; 1
Neumann (10.1016/j.ejor.2010.05.036_bib15) 2005; 165
Sourd (10.1016/j.ejor.2010.05.036_bib19) 2005; 165
References_xml – volume: 17
  start-page: 36
  year: 1992
  end-page: 42
  ident: bib10
  article-title: Approximation schemes for the restricted shortest path problem
  publication-title: Mathematics of Operations Research
– volume: 1
  start-page: 343
  year: 1977
  end-page: 362
  ident: bib12
  article-title: Complexity of machine scheduling problems
  publication-title: Annals of Discrete Mathematics
– volume: 5
  start-page: 236
  year: 1979
  end-page: 287
  ident: bib8
  article-title: Optimisation and approximation in deterministic sequencing and scheduling: a survey
  publication-title: Annals of Discrete Mathematics
– volume: 52
  start-page: 527
  year: 2005
  end-page: 535
  ident: bib9
  article-title: Basic scheduling problems with raw material constraints
  publication-title: Naval Research Logistics
– volume: 49
  start-page: 393
  year: 2005
  end-page: 412
  ident: bib13
  article-title: The parcel hub scheduling problem: a simulation-based solution approach
  publication-title: Computers and Industrial Engineering
– volume: 5
  start-page: 43
  year: 2002
  end-page: 69
  ident: bib3
  article-title: Heuristics for scheduling with inventory: dynamic focus via constraint criticality
  publication-title: Journal of Scheduling
– volume: 143
  start-page: 151
  year: 2003
  end-page: 188
  ident: bib11
  article-title: Algorithms for propagating resource constraints in ai planning and scheduling: existing approaches and new results
  publication-title: Artificial Intelligence
– volume: 28
  start-page: 151
  year: 2006
  end-page: 176
  ident: bib6
  article-title: Job-shop scheduling with limited capacity buffers
  publication-title: OR Spectrum
– volume: 157
  start-page: 3631
  year: 2009
  end-page: 3642
  ident: bib7
  article-title: The project scheduling problem with production and consumption of resources: a list-scheduling based algorithm
  publication-title: Discrete Applied Mathematics
– volume: 193
  start-page: 805
  year: 2009
  end-page: 819
  ident: bib2
  article-title: Scheduling tests in automotive R&D projects
  publication-title: European Journal of Operational Research
– volume: 25
  start-page: 549
  year: 2003
  end-page: 574
  ident: bib5
  article-title: Flow shop scheduling with intermediate buffers
  publication-title: OR Spectrum
– volume: 165
  start-page: 510
  year: 2005
  end-page: 524
  ident: bib19
  article-title: Continuous filling and emptying of storage systems in constraint-based scheduling
  publication-title: European Journal of Operational Research
– volume: 37
  start-page: 213
  year: 1990
  end-page: 223
  ident: bib1
  article-title: Faster algorithms for the shortest path problem
  publication-title: Journal of the Association for Computing Machinery
– volume: 27
  start-page: 533
  year: 1980
  end-page: 549
  ident: bib17
  article-title: Flow shop scheduling with limited temporary storage
  publication-title: Journal of the Association for Computing Machinery
– volume: 184
  start-page: 377
  year: 2008
  end-page: 396
  ident: bib20
  article-title: Scheduling of inbound and outbound trucks in cross docking systems with temporary storage
  publication-title: European Journal of Operational Research
– volume: 165
  start-page: 495
  year: 2005
  end-page: 509
  ident: bib15
  article-title: Scheduling of continuous and discontinuous material flows with intermediate storage restrictions
  publication-title: European Journal of Operational Research
– volume: 56
  start-page: 513
  year: 2002
  end-page: 533
  ident: bib14
  article-title: Project scheduling with inventory constraints
  publication-title: Mathematical Methods of Operations Research
– volume: 22
  start-page: 501
  year: 2000
  end-page: 524
  ident: bib18
  article-title: Batch scheduling in process industries: an application of resource-constrained project scheduling
  publication-title: OR Spectrum
– volume: 32
  start-page: 135
  year: 2010
  end-page: 161
  ident: bib4
  article-title: Scheduling inbound and outbound trucks at cross docking terminals
  publication-title: OR Spectrum
– volume: 116
  start-page: 205
  year: 1999
  end-page: 219
  ident: bib16
  article-title: The permutation shop with buffers: a tabu search approach
  publication-title: European Journal of Operational Research
– volume: 56
  start-page: 513
  year: 2002
  ident: 10.1016/j.ejor.2010.05.036_bib14
  article-title: Project scheduling with inventory constraints
  publication-title: Mathematical Methods of Operations Research
  doi: 10.1007/s001860200251
– volume: 116
  start-page: 205
  year: 1999
  ident: 10.1016/j.ejor.2010.05.036_bib16
  article-title: The permutation shop with buffers: a tabu search approach
  publication-title: European Journal of Operational Research
  doi: 10.1016/S0377-2217(98)00017-4
– volume: 165
  start-page: 510
  year: 2005
  ident: 10.1016/j.ejor.2010.05.036_bib19
  article-title: Continuous filling and emptying of storage systems in constraint-based scheduling
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2004.04.019
– volume: 5
  start-page: 43
  year: 2002
  ident: 10.1016/j.ejor.2010.05.036_bib3
  article-title: Heuristics for scheduling with inventory: dynamic focus via constraint criticality
  publication-title: Journal of Scheduling
  doi: 10.1002/jos.91
– volume: 165
  start-page: 495
  year: 2005
  ident: 10.1016/j.ejor.2010.05.036_bib15
  article-title: Scheduling of continuous and discontinuous material flows with intermediate storage restrictions
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2004.04.018
– volume: 49
  start-page: 393
  year: 2005
  ident: 10.1016/j.ejor.2010.05.036_bib13
  article-title: The parcel hub scheduling problem: a simulation-based solution approach
  publication-title: Computers and Industrial Engineering
  doi: 10.1016/j.cie.2005.07.002
– volume: 28
  start-page: 151
  year: 2006
  ident: 10.1016/j.ejor.2010.05.036_bib6
  article-title: Job-shop scheduling with limited capacity buffers
  publication-title: OR Spectrum
  doi: 10.1007/s00291-005-0008-1
– volume: 37
  start-page: 213
  year: 1990
  ident: 10.1016/j.ejor.2010.05.036_bib1
  article-title: Faster algorithms for the shortest path problem
  publication-title: Journal of the Association for Computing Machinery
  doi: 10.1145/77600.77615
– volume: 17
  start-page: 36
  issue: 1
  year: 1992
  ident: 10.1016/j.ejor.2010.05.036_bib10
  article-title: Approximation schemes for the restricted shortest path problem
  publication-title: Mathematics of Operations Research
  doi: 10.1287/moor.17.1.36
– volume: 143
  start-page: 151
  year: 2003
  ident: 10.1016/j.ejor.2010.05.036_bib11
  article-title: Algorithms for propagating resource constraints in ai planning and scheduling: existing approaches and new results
  publication-title: Artificial Intelligence
  doi: 10.1016/S0004-3702(02)00362-4
– volume: 184
  start-page: 377
  year: 2008
  ident: 10.1016/j.ejor.2010.05.036_bib20
  article-title: Scheduling of inbound and outbound trucks in cross docking systems with temporary storage
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2006.10.047
– volume: 27
  start-page: 533
  year: 1980
  ident: 10.1016/j.ejor.2010.05.036_bib17
  article-title: Flow shop scheduling with limited temporary storage
  publication-title: Journal of the Association for Computing Machinery
  doi: 10.1145/322203.322213
– volume: 1
  start-page: 343
  year: 1977
  ident: 10.1016/j.ejor.2010.05.036_bib12
  article-title: Complexity of machine scheduling problems
  publication-title: Annals of Discrete Mathematics
  doi: 10.1016/S0167-5060(08)70743-X
– volume: 25
  start-page: 549
  year: 2003
  ident: 10.1016/j.ejor.2010.05.036_bib5
  article-title: Flow shop scheduling with intermediate buffers
  publication-title: OR Spectrum
  doi: 10.1007/s00291-003-0133-7
– volume: 32
  start-page: 135
  year: 2010
  ident: 10.1016/j.ejor.2010.05.036_bib4
  article-title: Scheduling inbound and outbound trucks at cross docking terminals
  publication-title: OR Spectrum
  doi: 10.1007/s00291-008-0139-2
– volume: 22
  start-page: 501
  issue: 4
  year: 2000
  ident: 10.1016/j.ejor.2010.05.036_bib18
  article-title: Batch scheduling in process industries: an application of resource-constrained project scheduling
  publication-title: OR Spectrum
  doi: 10.1007/s002910000042
– volume: 157
  start-page: 3631
  year: 2009
  ident: 10.1016/j.ejor.2010.05.036_bib7
  article-title: The project scheduling problem with production and consumption of resources: a list-scheduling based algorithm
  publication-title: Discrete Applied Mathematics
  doi: 10.1016/j.dam.2009.02.012
– volume: 193
  start-page: 805
  issue: 3
  year: 2009
  ident: 10.1016/j.ejor.2010.05.036_bib2
  article-title: Scheduling tests in automotive R&D projects
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2007.11.010
– volume: 5
  start-page: 236
  year: 1979
  ident: 10.1016/j.ejor.2010.05.036_bib8
  article-title: Optimisation and approximation in deterministic sequencing and scheduling: a survey
  publication-title: Annals of Discrete Mathematics
– volume: 52
  start-page: 527
  year: 2005
  ident: 10.1016/j.ejor.2010.05.036_bib9
  article-title: Basic scheduling problems with raw material constraints
  publication-title: Naval Research Logistics
  doi: 10.1002/nav.20095
SSID ssj0001515
Score 2.2118964
Snippet This paper focuses on single machine scheduling subject to inventory constraints. Jobs either add items to an inventory or remove items from that inventory....
SourceID proquest
repec
pascalfrancis
econis
crossref
elsevier
SourceType Aggregation Database
Index Database
Enrichment Source
Publisher
StartPage 605
SubjectTerms Applied sciences
Completion time
Complexity
Complexity theory
Computation
Computational complexity
Exact sciences and technology
Inventories
Inventory constraints
Inventory control, production control. Distribution
Inventory management
Job shops
Lateness
Machine scheduling
Machine scheduling Inventory constraints Computational complexity Strong NP-hardness Polynomial-time algorithms
Operational research
Operational research and scientific management
Operational research. Management science
Optimization
Optimization algorithms
Polynomial-time algorithms
Production scheduling
Scheduling
Scheduling, sequencing
Stockpiling
Strong NP-hardness
Studies
Title Complexity of single machine scheduling subject to nonnegative inventory constraints
URI https://dx.doi.org/10.1016/j.ejor.2010.05.036
http://www.econis.eu/PPNSET?PPN=635289539
http://econpapers.repec.org/article/eeeejores/v_3a207_3ay_3a2010_3ai_3a2_3ap_3a605-619.htm
https://www.proquest.com/docview/745951407
https://www.proquest.com/docview/760210939
Volume 207
WOSCitedRecordID wos000281107200007&url=https%3A%2F%2Fcvtisr.summon.serialssolutions.com%2F%23%21%2Fsearch%3Fho%3Df%26include.ft.matches%3Dt%26l%3Dnull%26q%3D
hasFullText 1
inHoldings 1
isFullTextHit
isPrint
journalDatabaseRights – providerCode: PRVESC
  databaseName: Elsevier SD Freedom Collection Journals 2021
  customDbUrl:
  eissn: 1872-6860
  dateEnd: 99991231
  omitProxy: false
  ssIdentifier: ssj0001515
  issn: 0377-2217
  databaseCode: AIEXJ
  dateStart: 19950105
  isFulltext: true
  titleUrlDefault: https://www.sciencedirect.com
  providerName: Elsevier
link http://cvtisr.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwtV3db9MwELdKOyEQ4qOAVgaTH3ibMsVJHCePWxniQ5p4KFLfrDh11paSVP3S9rfwz3IXO2laxsQeqJQoclPXyd35Pvy7MyHvYyWEDlzlRB5Gq9woc1TicicQWgWg7_xMZOVmE-LyMhoO42-t1q8qF2YzE3keXV_H8_9KamgDYmPq7D3IXXcKDXANRIczkB3O_0R4lHCscmmgFhgKmCFIFTGT-gR8WdAtZQr6cq0wBoPGZ45olytTAnxSotBx5T1F0xF3kDDFnm6N31tbFhoWVVTRlg-qw8zniF4vDGYYJtg6M6g_LkokwfkNzDdOf6yLfXTQ1yS_UsWPbeu6gg-XqxaNeMUO9sPmaQnheJ7J2KzmYM9sfWuZzWvMqKHLG8o5NPPrH_O-CUFMT_W0WFi8Hj91_VuKbO8pvxqSWKHdphL7kNiHdLmEPh6Qjid4HLVJ5-zzxfBLrejRFiwXqewD2ZwsAx_cH8mO3XOAwY7JcscAejJPliCWmdlPZcfh6Sz0XKcNu2fwnDy1Dgs9M4z2grR03iUPq3yJLnlW7QtCrZrokseNIpcvyWDLkLTIqGFIahmSbhmSWoakq4I2GJLWDEkbDPmKfP94Meh_cuxeHk4KJuXKUYJl2ldKjQRjImVJKOI4jXzGUnDxdcx9UAwC3IUk1JpnoctG4MowBVohS5XI_NekDf-tDwl1WaY495LIT0cBT8DFATMzTdiIgS0vhNsjrHrTMrWF7nFwM_l3GvfISf2buSnzcufdh4aA9b0hFkmCh4h7hFckldaGNbapBFa9s8vjHfrXPYP_xUTgiR45qhhCWvleShFw8JACF76l9begH3DRL8l1sYZbQozqxDiyDyUb1T1r-MAo9FJupJ-ABML5pryCUfnJBC_hmMMBQihB9OR49fPNvd7UEXm0nQPekvZqsdbvyEG6WU2Wi2MrUL8BTI73UQ
linkProvider Elsevier
openUrl ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Ajournal&rft.genre=article&rft.atitle=Complexity+of+single+machine+scheduling+subject+to+nonnegative+inventory+constraints&rft.jtitle=European+journal+of+operational+research&rft.au=Briskorn%2C+Dirk&rft.au=Choi%2C+Byung-Cheon&rft.au=Lee%2C+Kangbok&rft.au=Leung%2C+Joseph&rft.date=2010-12-01&rft.issn=0377-2217&rft.volume=207&rft.issue=2&rft.spage=605&rft.epage=619&rft_id=info:doi/10.1016%2Fj.ejor.2010.05.036&rft.externalDBID=n%2Fa&rft.externalDocID=10_1016_j_ejor_2010_05_036
thumbnail_l http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/lc.gif&issn=0377-2217&client=summon
thumbnail_m http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/mc.gif&issn=0377-2217&client=summon
thumbnail_s http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/sc.gif&issn=0377-2217&client=summon