Extending the Multimode Resource-Constrained Project Scheduling Problem by Including Value Considerations

The current trend in modern project management methodologies is to maximize project values. We suggest a quantitative model that balances time, cost, and value. It generates detailed project plans, which are feasible with respect to time, cost, and resource-constraints, and considers interactions be...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:IEEE transactions on engineering management Jg. 63; H. 1; S. 4 - 15
Hauptverfasser: Balouka, Noemie, Cohen, Izak, Shtub, Avraham
Format: Journal Article
Sprache:Englisch
Veröffentlicht: New York IEEE 01.02.2016
The Institute of Electrical and Electronics Engineers, Inc. (IEEE)
Schlagworte:
ISSN:0018-9391, 1558-0040
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:The current trend in modern project management methodologies is to maximize project values. We suggest a quantitative model that balances time, cost, and value. It generates detailed project plans, which are feasible with respect to time, cost, and resource-constraints, and considers interactions between technical performance, time, and cost. Such interactions, which existing project management models typically ignore or project managers deal with intuitively, are important for increasing projects' values. The model, which extends the multimode resource-constrained project scheduling problem by including value, generates an efficient frontier that includes the best project plans for varying project costs. We provide illustrative examples to demonstrate the suggested approach.
Bibliographie:SourceType-Scholarly Journals-1
ObjectType-Feature-1
content type line 14
ObjectType-Article-1
ObjectType-Feature-2
content type line 23
ISSN:0018-9391
1558-0040
DOI:10.1109/TEM.2015.2497209