Propose a Polynomial Time Algorithm for Total Completion Time Objective

In this study, we integrate deteriorate jobs with repair&maintenance activity on a single machine scheduling subject to total completion time. This work has more than one motivation. First, jobs are assigned to machines in an automated production line. Later, to schedule the maintenance activiti...

Celý popis

Uložené v:
Podrobná bibliografia
Vydané v:International journal of mathematical, engineering and management sciences Ročník 6; číslo 3; s. 932 - 943
Hlavní autori: Ozturkoglu, Yucel, Ozturkoglu, Omer
Médium: Journal Article
Jazyk:English
Vydavateľské údaje: Dehradun International Journal of Mathematical, Engineering and Management Sciences 01.06.2021
Ram Arti Publishers
Predmet:
ISSN:2455-7749, 2455-7749
On-line prístup:Získať plný text
Tagy: Pridať tag
Žiadne tagy, Buďte prvý, kto otaguje tento záznam!
Popis
Shrnutí:In this study, we integrate deteriorate jobs with repair&maintenance activity on a single machine scheduling subject to total completion time. This work has more than one motivation. First, jobs are assigned to machines in an automated production line. Later, to schedule the maintenance activities, if needed, to prevent machinery from breaking down later. There are some important mathematical models to solve this combination. However, due to the complexity of the problem which is Np-hard, a polynomial algorithm should be needed for solving large problems. Therefore, this article introduces several polnomial algorithms to determine the order of things best. With using these algorithms, it will be possible to determine where to assign to the schedule, taking into account the number of maintenance activities required and their optimum total completion time.
Bibliografia:ObjectType-Article-1
SourceType-Scholarly Journals-1
ObjectType-Feature-2
content type line 14
ISSN:2455-7749
2455-7749
DOI:10.33889/IJMEMS.2021.6.3.055