A Multi-Objective Mathematical Programming Model for Project-Scheduling Optimization Considering Customer Satisfaction in Construction Projects
The aim of this study was to develop a multi-objective mathematical programming model for the trade-off of time, cost, and quality in the project-scheduling problem (PSP) by taking priorities and resource constraints as well as activity preemption into account. First, a small-sized problem instance...
Uloženo v:
| Vydáno v: | Mathematics (Basel) Ročník 12; číslo 2; s. 211 |
|---|---|
| Hlavní autoři: | , , , , , , |
| Médium: | Journal Article |
| Jazyk: | angličtina |
| Vydáno: |
Basel
MDPI AG
01.01.2024
|
| Témata: | |
| ISSN: | 2227-7390, 2227-7390 |
| On-line přístup: | Získat plný text |
| Tagy: |
Přidat tag
Žádné tagy, Buďte první, kdo vytvoří štítek k tomuto záznamu!
|
| Abstract | The aim of this study was to develop a multi-objective mathematical programming model for the trade-off of time, cost, and quality in the project-scheduling problem (PSP) by taking priorities and resource constraints as well as activity preemption into account. First, a small-sized problem instance that was a sub-project of an oil and gas construction project was used for te validation of the proposed model and algorithm. Subsequently, considering the sensitivity, complexity, and importance of oil and gas projects, the proposed model was implemented in a large-sized oil and gas construction project. Considering the NP-hardness of this problem, the NSGA-II metaheuristic algorithm was used to deal with the time, cost, and quality trade-off problem. Finally, a sensitivity analysis was implemented on the three main parameters of time, cost, and quality to investigate the effects of changes on the results. The findings show that the proposed model is more sensitive to cost changes, so an increase in project costs leads to a drastic change in the values of other objective functions. |
|---|---|
| AbstractList | The aim of this study was to develop a multi-objective mathematical programming model for the trade-off of time, cost, and quality in the project-scheduling problem (PSP) by taking priorities and resource constraints as well as activity preemption into account. First, a small-sized problem instance that was a sub-project of an oil and gas construction project was used for te validation of the proposed model and algorithm. Subsequently, considering the sensitivity, complexity, and importance of oil and gas projects, the proposed model was implemented in a large-sized oil and gas construction project. Considering the NP-hardness of this problem, the NSGA-II metaheuristic algorithm was used to deal with the time, cost, and quality trade-off problem. Finally, a sensitivity analysis was implemented on the three main parameters of time, cost, and quality to investigate the effects of changes on the results. The findings show that the proposed model is more sensitive to cost changes, so an increase in project costs leads to a drastic change in the values of other objective functions. |
| Audience | Academic |
| Author | Khalilzadeh, Mohammad Antucheviciene, Jurgita Amiri, Maghsoud Zohrehvandi, Shakib Zavadskas, Edmundas Kazimieras Zohrehvandi, Mehrnoosh Jolai, Fariborz |
| Author_xml | – sequence: 1 givenname: Mehrnoosh surname: Zohrehvandi fullname: Zohrehvandi, Mehrnoosh – sequence: 2 givenname: Shakib orcidid: 0000-0003-2462-999X surname: Zohrehvandi fullname: Zohrehvandi, Shakib – sequence: 3 givenname: Mohammad orcidid: 0000-0002-2373-8505 surname: Khalilzadeh fullname: Khalilzadeh, Mohammad – sequence: 4 givenname: Maghsoud surname: Amiri fullname: Amiri, Maghsoud – sequence: 5 givenname: Fariborz orcidid: 0000-0003-0824-8513 surname: Jolai fullname: Jolai, Fariborz – sequence: 6 givenname: Edmundas Kazimieras orcidid: 0000-0002-3201-949X surname: Zavadskas fullname: Zavadskas, Edmundas Kazimieras – sequence: 7 givenname: Jurgita orcidid: 0000-0002-1734-3216 surname: Antucheviciene fullname: Antucheviciene, Jurgita |
| BookMark | eNptUctq3DAUNSWFpml2_QBDt3Uqy5ItL4ehj0CGKaRdCz2uJhpsayrJhfQn-su9HqcQSnUXku55IJ37uriYwgRF8bYmN03Tkw-jyg81JVh1_aK4pJR2VYfAxbPzq-I6pSPB1deNYP1l8XtT7uYh-2qvj2Cy_wnlDo0A3bxRQ_k1hkNU4-inQ7kLFobShbh0F3Z1bx7AzsMC7k_Zj_4XysJUbsOUvIW4ANs55TBCLO8RS06ZM8OvpBzn9f7kmN4UL50aElw_7VfF908fv22_VHf7z7fbzV1lGGlzpcER6LVgmteuJ4JbqpVjNbQM6p4T0XNtgCvqdMtYJ7RpiGa95pZroUjXXBW3q68N6ihP0Y8qPsqgvDw3QjxIFTGCAaRBC2us5sIaxkEpy4A3GKfiFkSr0Ovd6nWK4ccMKctjmOOEz5e0r0UnMO8WWTcr66DQ1E8u5KgMloXRG5yl89jfIBsVglIU0FVgYkgpgpPG53O-KPSDrIlcBi-fDx5F7_8R_f3bf-l_AB2dtMo |
| CitedBy_id | crossref_primary_10_3390_infrastructures9020024 crossref_primary_10_3390_app15084089 |
| Cites_doi | 10.1016/j.cor.2019.05.004 10.1007/s10668-022-02370-y 10.1287/opre.9.3.296 10.1016/j.autcon.2018.09.009 10.1016/S0263-7863(98)00043-X 10.1016/j.eswa.2023.121660 10.3390/sym13122402 10.1016/j.ejor.2019.02.030 10.1061/(ASCE)CO.1943-7862.0001451 10.1080/00207543.2022.2074322 10.1007/978-3-030-24835-2 10.1016/0377-2217(94)00202-9 10.3390/su131910922 10.1016/j.eswa.2013.08.081 10.1016/j.aci.2014.02.003 10.1108/ECAM-02-2021-0177 10.1287/mnsc.20.6.990 10.1016/j.ijproman.2011.05.004 10.1016/j.jngse.2017.04.033 10.3390/sym12040594 10.1108/JEDT-11-2020-0463 10.3390/su10030680 10.1007/s12667-019-00374-8 10.1080/09544120050135533 10.1061/(ASCE)0733-9364(2005)131:4(477) 10.1016/j.eswa.2014.11.032 |
| ContentType | Journal Article |
| Copyright | COPYRIGHT 2024 MDPI AG 2024 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/). Notwithstanding the ProQuest Terms and Conditions, you may use this content in accordance with the terms of the License. |
| Copyright_xml | – notice: COPYRIGHT 2024 MDPI AG – notice: 2024 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/). Notwithstanding the ProQuest Terms and Conditions, you may use this content in accordance with the terms of the License. |
| DBID | AAYXX CITATION 3V. 7SC 7TB 7XB 8AL 8FD 8FE 8FG 8FK ABJCF ABUWG AFKRA ARAPS AZQEC BENPR BGLVJ CCPQU DWQXO FR3 GNUQQ HCIFZ JQ2 K7- KR7 L6V L7M L~C L~D M0N M7S P62 PHGZM PHGZT PIMPY PKEHL PQEST PQGLB PQQKQ PQUKI PRINS PTHSS Q9U DOA |
| DOI | 10.3390/math12020211 |
| DatabaseName | CrossRef ProQuest Central (Corporate) Computer and Information Systems Abstracts Mechanical & Transportation Engineering Abstracts ProQuest Central (purchase pre-March 2016) Computing Database (Alumni Edition) Technology Research Database ProQuest SciTech Collection ProQuest Technology Collection ProQuest Central (Alumni) (purchase pre-March 2016) Materials Science & Engineering Collection ProQuest Central (Alumni) ProQuest Central UK/Ireland Advanced Technologies & Computer Science Collection ProQuest Central Essentials ProQuest Central Technology Collection ProQuest One Community College ProQuest Central Korea Engineering Research Database ProQuest Central Student SciTech Premium Collection ProQuest Computer Science Collection Computer Science Database Civil Engineering Abstracts ProQuest Engineering Collection Advanced Technologies Database with Aerospace Computer and Information Systems Abstracts Academic Computer and Information Systems Abstracts Professional Computing Database Engineering Database ProQuest Advanced Technologies & Aerospace Collection ProQuest Central Premium ProQuest One Academic (New) Publicly Available Content Database ProQuest One Academic Middle East (New) ProQuest One Academic Eastern Edition (DO NOT USE) One Applied & Life Sciences ProQuest One Academic (retired) ProQuest One Academic UKI Edition ProQuest Central China Engineering Collection ProQuest Central Basic DOAJ Directory of Open Access Journals |
| DatabaseTitle | CrossRef Publicly Available Content Database Computer Science Database ProQuest Central Student Technology Collection Technology Research Database Computer and Information Systems Abstracts – Academic ProQuest One Academic Middle East (New) Mechanical & Transportation Engineering Abstracts ProQuest Advanced Technologies & Aerospace Collection ProQuest Central Essentials ProQuest Computer Science Collection Computer and Information Systems Abstracts ProQuest Central (Alumni Edition) SciTech Premium Collection ProQuest One Community College ProQuest Central China ProQuest Central ProQuest One Applied & Life Sciences ProQuest Engineering Collection ProQuest Central Korea ProQuest Central (New) Advanced Technologies Database with Aerospace Engineering Collection Advanced Technologies & Aerospace Collection Civil Engineering Abstracts ProQuest Computing Engineering Database ProQuest Central Basic ProQuest Computing (Alumni Edition) ProQuest One Academic Eastern Edition ProQuest Technology Collection ProQuest SciTech Collection Computer and Information Systems Abstracts Professional ProQuest One Academic UKI Edition Materials Science & Engineering Collection Engineering Research Database ProQuest One Academic ProQuest One Academic (New) ProQuest Central (Alumni) |
| DatabaseTitleList | Publicly Available Content Database CrossRef |
| Database_xml | – sequence: 1 dbid: DOA name: DOAJ Directory of Open Access Journals url: https://www.doaj.org/ sourceTypes: Open Website – sequence: 2 dbid: PIMPY name: Publicly Available Content Database url: http://search.proquest.com/publiccontent sourceTypes: Aggregation Database |
| DeliveryMethod | fulltext_linktorsrc |
| Discipline | Mathematics |
| EISSN | 2227-7390 |
| ExternalDocumentID | oai_doaj_org_article_cb64dcdb58dc45eaad4e53739a5de86a A780878822 10_3390_math12020211 |
| GeographicLocations | Iran |
| GeographicLocations_xml | – name: Iran |
| GroupedDBID | -~X 5VS 85S 8FE 8FG AADQD AAFWJ AAYXX ABDBF ABJCF ABPPZ ABUWG ACIPV ACIWK ADBBV AFFHD AFKRA AFPKN AFZYC ALMA_UNASSIGNED_HOLDINGS AMVHM ARAPS AZQEC BCNDV BENPR BGLVJ BPHCQ CCPQU CITATION DWQXO GNUQQ GROUPED_DOAJ HCIFZ IAO ITC K6V K7- KQ8 L6V M7S MODMG M~E OK1 PHGZM PHGZT PIMPY PQGLB PQQKQ PROAC PTHSS RNS 3V. 7SC 7TB 7XB 8AL 8FD 8FK FR3 JQ2 KR7 L7M L~C L~D M0N P62 PKEHL PQEST PQUKI PRINS Q9U |
| ID | FETCH-LOGICAL-c406t-bef0e9b84b51f9085d2baf41e64e1950895bce5a2fb64478bc30b49b5d5b8a073 |
| IEDL.DBID | DOA |
| ISICitedReferencesCount | 2 |
| ISICitedReferencesURI | http://www.webofscience.com/api/gateway?GWVersion=2&SrcApp=Summon&SrcAuth=ProQuest&DestLinkType=CitingArticles&DestApp=WOS_CPL&KeyUT=001150828900001&url=https%3A%2F%2Fcvtisr.summon.serialssolutions.com%2F%23%21%2Fsearch%3Fho%3Df%26include.ft.matches%3Dt%26l%3Dnull%26q%3D |
| ISSN | 2227-7390 |
| IngestDate | Fri Oct 03 12:53:03 EDT 2025 Sun Jul 13 04:39:06 EDT 2025 Tue Nov 04 18:40:00 EST 2025 Tue Nov 18 21:14:22 EST 2025 Sat Nov 29 07:09:49 EST 2025 |
| IsDoiOpenAccess | true |
| IsOpenAccess | true |
| IsPeerReviewed | true |
| IsScholarly | true |
| Issue | 2 |
| Language | English |
| LinkModel | DirectLink |
| MergedId | FETCHMERGED-LOGICAL-c406t-bef0e9b84b51f9085d2baf41e64e1950895bce5a2fb64478bc30b49b5d5b8a073 |
| Notes | ObjectType-Article-1 SourceType-Scholarly Journals-1 ObjectType-Feature-2 content type line 14 |
| ORCID | 0000-0002-1734-3216 0000-0003-0824-8513 0000-0002-3201-949X 0000-0003-2462-999X 0000-0002-2373-8505 |
| OpenAccessLink | https://doaj.org/article/cb64dcdb58dc45eaad4e53739a5de86a |
| PQID | 2918780006 |
| PQPubID | 2032364 |
| ParticipantIDs | doaj_primary_oai_doaj_org_article_cb64dcdb58dc45eaad4e53739a5de86a proquest_journals_2918780006 gale_infotracacademiconefile_A780878822 crossref_citationtrail_10_3390_math12020211 crossref_primary_10_3390_math12020211 |
| PublicationCentury | 2000 |
| PublicationDate | 2024-01-01 |
| PublicationDateYYYYMMDD | 2024-01-01 |
| PublicationDate_xml | – month: 01 year: 2024 text: 2024-01-01 day: 01 |
| PublicationDecade | 2020 |
| PublicationPlace | Basel |
| PublicationPlace_xml | – name: Basel |
| PublicationTitle | Mathematics (Basel) |
| PublicationYear | 2024 |
| Publisher | MDPI AG |
| Publisher_xml | – name: MDPI AG |
| References | Creemers (ref_7) 2019; 277 Aluko (ref_22) 2020; 19 Olatunde (ref_35) 2017; 15 Ammar (ref_14) 2019; 22 Farughi (ref_26) 2018; 31 Tareghian (ref_5) 2006; 181 ref_11 ref_32 Sajedi (ref_29) 2018; 50 Eirgash (ref_41) 2019; 71 Alavipour (ref_4) 2019; 98 Maghsoudlou (ref_8) 2020; 12 Kim (ref_34) 2012; 30 Moniri (ref_42) 2020; 19 ref_16 ref_38 Banihashemi (ref_39) 2023; 25 ref_15 Demir (ref_43) 2024; 237 Babu (ref_2) 1996; 88 Kelley (ref_31) 1961; 9 Tavana (ref_1) 2014; 41 Roghanian (ref_13) 2018; 18 Wood (ref_37) 2017; 45 (ref_10) 2018; 14 Khang (ref_17) 1999; 17 Ghasemi (ref_27) 2023; 61 Alavipour (ref_19) 2018; 144 Aluko (ref_23) 2021; 20 ref_46 ref_45 ref_44 Cheraghi (ref_30) 2023; 30 ref_20 Kristensen (ref_21) 2000; 11 ref_40 Bagheri (ref_6) 2018; 8 Ogbu (ref_24) 2021; 20 ref_28 Kandil (ref_3) 2005; 131 Hu (ref_36) 2014; 2014 Vanhoucke (ref_9) 2019; 109 Monghasemi (ref_25) 2015; 42 Sarkar (ref_12) 2020; 22 Diehlmann (ref_18) 2021; 20 Patterson (ref_33) 1974; 20 |
| References_xml | – volume: 109 start-page: 230 year: 2019 ident: ref_9 article-title: Resource-constrained project scheduling with activity splitting and setup times publication-title: Comput. Oper. Res. doi: 10.1016/j.cor.2019.05.004 – volume: 22 start-page: 1818 year: 2020 ident: ref_12 article-title: Risk analysis by integrated fuzzy expected value method and fuzzy failure mode and effect analysis for an elevated metro rail project of Ahmedabad, India publication-title: Int. J. Constr. Manag. – volume: 25 start-page: 7737 year: 2023 ident: ref_39 article-title: Towards sustainable project scheduling with reducing environmental pollution of projects: Fuzzy multi-objective programming approach to a case study of Eastern Iran publication-title: Environ. Dev. Sustain. doi: 10.1007/s10668-022-02370-y – volume: 2014 start-page: 673248 year: 2014 ident: ref_36 article-title: An innovative time, cost, and quality tradeoff modeling of building construction project based on resource allocation publication-title: Sci. World J. – volume: 9 start-page: 296 year: 1961 ident: ref_31 article-title: Critical-path planning and scheduling: Mathematical basis publication-title: Oper. Res. doi: 10.1287/opre.9.3.296 – volume: 20 start-page: 1519 year: 2021 ident: ref_24 article-title: Influence of selection criteria on clients’ satisfaction with construction consultancy services in Nigeria publication-title: J. Eng. Des. Technol. – ident: ref_32 – volume: 19 start-page: 966 year: 2020 ident: ref_42 article-title: Turnaround project risk assessment using hybrid fuzzy SWARA and EDAS method: Case of upstream oil process industries in Iran publication-title: J. Eng. Des. Technol. – volume: 98 start-page: 110 year: 2019 ident: ref_4 article-title: Time-cost tradeoff analysis with minimized project financing cost publication-title: Autom. Constr. doi: 10.1016/j.autcon.2018.09.009 – volume: 20 start-page: 543 year: 2021 ident: ref_18 article-title: Including decision-makers preferences in the cost-deprivation trade-off during disaster interventions publication-title: J. Eng. Des. Technol. – volume: 17 start-page: 249 year: 1999 ident: ref_17 article-title: Time, cost and quality trade-off in project management: A case study publication-title: Int. J. Proj. Manag. doi: 10.1016/S0263-7863(98)00043-X – volume: 15 start-page: 619 year: 2017 ident: ref_35 article-title: Quantitative appraisal of cost and time performance of construction projects in public and private universities in Osun State, Nigeria publication-title: J. Eng. Des. Technol. – volume: 237 start-page: 121660 year: 2024 ident: ref_43 article-title: Sensitivity analysis in multi-criteria decision making: A state-of-the-art research perspective using bibliometric analysis publication-title: Expert Syst. Appl. doi: 10.1016/j.eswa.2023.121660 – ident: ref_16 – ident: ref_38 doi: 10.3390/sym13122402 – volume: 277 start-page: 238 year: 2019 ident: ref_7 article-title: The preemptive stochastic resource-constrained project scheduling problem publication-title: Eur. J. Oper. Res. doi: 10.1016/j.ejor.2019.02.030 – volume: 50 start-page: 1003 year: 2018 ident: ref_29 article-title: Optimization of Time and Cost in Establishment of Temporary Accommodations after the Crisis publication-title: Amirkabir J. Civ. Eng. – volume: 144 start-page: 04018012 year: 2018 ident: ref_19 article-title: Optimizing financing cost in construction projects with fixed project duration publication-title: J. Constr. Eng. Manag. doi: 10.1061/(ASCE)CO.1943-7862.0001451 – ident: ref_44 – volume: 19 start-page: 557 year: 2020 ident: ref_22 article-title: Relationship between perceived service quality and client satisfaction indicators of engineering consultancy services in building projects publication-title: J. Eng. Des. Technol. – volume: 61 start-page: 2963 year: 2023 ident: ref_27 article-title: A new approach for production project scheduling with time, cost, and quality trade-off considering multi-mode resource-constraints under interval uncertainty publication-title: Int. J. Prod. Res. doi: 10.1080/00207543.2022.2074322 – ident: ref_45 doi: 10.1007/978-3-030-24835-2 – volume: 88 start-page: 320 year: 1996 ident: ref_2 article-title: Project management with time, cost, and quality considerations publication-title: Eur. J. Oper. Res. doi: 10.1016/0377-2217(94)00202-9 – ident: ref_28 doi: 10.3390/su131910922 – volume: 41 start-page: 1830 year: 2014 ident: ref_1 article-title: A new multi-objective multi-mode model for solving preemptive time–cost–quality trade-off project scheduling problems publication-title: Expert Syst. Appl. doi: 10.1016/j.eswa.2013.08.081 – volume: 14 start-page: 192 year: 2018 ident: ref_10 article-title: A solution procedure for preemptive multi-mode project scheduling problem with mode changeability to resumption publication-title: Appl. Comput. Inform. doi: 10.1016/j.aci.2014.02.003 – volume: 8 start-page: 83 year: 2018 ident: ref_6 article-title: Scheduling of construction projects using a combination of multi-objective programming and optimization via simulation publication-title: J. Prod. Oper. Manag. – volume: 31 start-page: 780 year: 2018 ident: ref_26 article-title: Project scheduling with simultaneous optimization, time, net present value, and project flexibility for multimode activities with constrained renewable resources publication-title: Int. J. Eng. – volume: 30 start-page: 1578 year: 2023 ident: ref_30 article-title: A multiproject scheduling and resource management model in projects construction publication-title: Eng. Constr. Archit. Manag. doi: 10.1108/ECAM-02-2021-0177 – volume: 20 start-page: 990 year: 1974 ident: ref_33 article-title: A horizon-varying, zero-one approach to project scheduling publication-title: Manag. Sci. doi: 10.1287/mnsc.20.6.990 – ident: ref_46 – volume: 30 start-page: 264 year: 2012 ident: ref_34 article-title: A practical approach to project scheduling: Considering the potential quality loss cost in the time–cost tradeoff problem publication-title: Int. J. Proj. Manag. doi: 10.1016/j.ijproman.2011.05.004 – volume: 45 start-page: 143 year: 2017 ident: ref_37 article-title: Gas and oil project time, cost, and quality tradeoff: Integrated stochastic and fuzzy multi-objective optimization applying a memetic, nondominated, sorting algorithm publication-title: J. Nat. Gas Sci. Eng. doi: 10.1016/j.jngse.2017.04.033 – ident: ref_15 doi: 10.3390/sym12040594 – volume: 20 start-page: 1057 year: 2021 ident: ref_23 article-title: Perceived service quality of architectural consultancy firms and client satisfaction in building projects in Nigeria publication-title: J. Eng. Des. Technol. – volume: 71 start-page: 139 year: 2019 ident: ref_41 article-title: A multi-objective decision-making model based on TLBO for the time–cost trade-off problems publication-title: Struct. Eng. Mech. – ident: ref_11 doi: 10.1108/JEDT-11-2020-0463 – volume: 181 start-page: 1305 year: 2006 ident: ref_5 article-title: On the discrete time, cost and quality trade-off problem publication-title: Appl. Math. Comput. – volume: 22 start-page: 252 year: 2019 ident: ref_14 article-title: Criticality measurement in fuzzy project scheduling publication-title: Int. J. Constr. Manag. – ident: ref_40 doi: 10.3390/su10030680 – volume: 18 start-page: 1 year: 2018 ident: ref_13 article-title: An improved fuzzy critical chain approach in order to face uncertainty in project scheduling publication-title: Int. J. Constr. Manag. – volume: 12 start-page: 431 year: 2020 ident: ref_8 article-title: A framework for preemptive multi-skilled project scheduling problem with time-of-use energy tariffs publication-title: Energy Syst. doi: 10.1007/s12667-019-00374-8 – volume: 11 start-page: 1007 year: 2000 ident: ref_21 article-title: Customer satisfaction measurement at post Denmark: Results of application of the European customer satisfaction index methodology publication-title: Total Qual. Manag. doi: 10.1080/09544120050135533 – volume: 131 start-page: 477 year: 2005 ident: ref_3 article-title: Time, cost, and quality trade-off analysis for highway construction publication-title: J. Constr. Eng. Manag. doi: 10.1061/(ASCE)0733-9364(2005)131:4(477) – ident: ref_20 – volume: 42 start-page: 3089 year: 2015 ident: ref_25 article-title: A novel multi criteria decision making model for optimizing time–cost–quality trade-off problems in construction projects publication-title: Expert Syst. Appl. doi: 10.1016/j.eswa.2014.11.032 |
| SSID | ssj0000913849 |
| Score | 2.2702243 |
| Snippet | The aim of this study was to develop a multi-objective mathematical programming model for the trade-off of time, cost, and quality in the project-scheduling... |
| SourceID | doaj proquest gale crossref |
| SourceType | Open Website Aggregation Database Enrichment Source Index Database |
| StartPage | 211 |
| SubjectTerms | activity preemption Algorithms Cost analysis Customer satisfaction Heuristic methods Integer programming Linear programming Mathematical models Mathematical programming Mechanical properties multi-objective optimization model Multiple objective analysis NSGA-II Optimization Parameter sensitivity Production planning project planning Research methodology Scheduling Sensitivity analysis time, cost, and quality trade-off Tradeoffs |
| SummonAdditionalLinks | – databaseName: Engineering Database dbid: M7S link: http://cvtisr.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwpV1NT9wwEB0V2gMc2lKo2JZWPoA4IItNYm_sU7VFRT20gLRQcbP8FdqK3YVd4G_0L3fGcRZ6oBeu8dhyNJM3Y2fmDcB20ffRiUpwFVXgogwNd77yvK4GqtQFuoRUPvbjW310pM7P9Um-cJvntMoOExNQh6mnO_J9nKhqRej66eqaU9co-ruaW2gswXNiSShS6t5occdCnJdK6DbfvcLT_T5GgT8LPO-jZyv-8USJsP8xWE6-5vDVU3f5Gl7mKJMNW7NYg2dx8gZWvy8oWufr8GfIUvEtP3a_W9Bj9-M496RN3Bqja2PUMO2SYXhLT0maj1DXgZLYL9gxgs44V3Oyrv8nDRzcYmA5jjM2elBBwX61Qh1tbbfifAPODr-cHnzluTsD9xgE3HAXm37UTgkni0Zj5BZKZxtRxIGIqbesls5HacvGYcxVKzSBvhPaySCdsogsb2F5Mp3ETWAqUiCKE4oaF6hqbXGKs06VFheS_R7sdZoyPlOXUweNS4NHGNKreajXHuwspK9ayo5H5D6T0hcyRLSdHkxnFyZ_t8bjToIPTqrghYzWBhFlVVfayhDVwPZgl0zGEBzglrzNVQ34YkSsZYZoDWgRGIb1YKszGZNxYm7u7eXd_4ffwwpuWrSXP1uwjFqKH-CFv0MFzj4ms_8L65cPoA priority: 102 providerName: ProQuest |
| Title | A Multi-Objective Mathematical Programming Model for Project-Scheduling Optimization Considering Customer Satisfaction in Construction Projects |
| URI | https://www.proquest.com/docview/2918780006 https://doaj.org/article/cb64dcdb58dc45eaad4e53739a5de86a |
| Volume | 12 |
| WOSCitedRecordID | wos001150828900001&url=https%3A%2F%2Fcvtisr.summon.serialssolutions.com%2F%23%21%2Fsearch%3Fho%3Df%26include.ft.matches%3Dt%26l%3Dnull%26q%3D |
| hasFullText | 1 |
| inHoldings | 1 |
| isFullTextHit | |
| isPrint | |
| journalDatabaseRights | – providerCode: PRVAON databaseName: DOAJ Directory of Open Access Journals customDbUrl: eissn: 2227-7390 dateEnd: 99991231 omitProxy: false ssIdentifier: ssj0000913849 issn: 2227-7390 databaseCode: DOA dateStart: 20130101 isFulltext: true titleUrlDefault: https://www.doaj.org/ providerName: Directory of Open Access Journals – providerCode: PRVHPJ databaseName: ROAD: Directory of Open Access Scholarly Resources customDbUrl: eissn: 2227-7390 dateEnd: 99991231 omitProxy: false ssIdentifier: ssj0000913849 issn: 2227-7390 databaseCode: M~E dateStart: 20130101 isFulltext: true titleUrlDefault: https://road.issn.org providerName: ISSN International Centre – providerCode: PRVPQU databaseName: Computer Science Database customDbUrl: eissn: 2227-7390 dateEnd: 99991231 omitProxy: false ssIdentifier: ssj0000913849 issn: 2227-7390 databaseCode: K7- dateStart: 20130301 isFulltext: true titleUrlDefault: http://search.proquest.com/compscijour providerName: ProQuest – providerCode: PRVPQU databaseName: Engineering Database customDbUrl: eissn: 2227-7390 dateEnd: 99991231 omitProxy: false ssIdentifier: ssj0000913849 issn: 2227-7390 databaseCode: M7S dateStart: 20130301 isFulltext: true titleUrlDefault: http://search.proquest.com providerName: ProQuest – providerCode: PRVPQU databaseName: Proquest Central customDbUrl: eissn: 2227-7390 dateEnd: 99991231 omitProxy: false ssIdentifier: ssj0000913849 issn: 2227-7390 databaseCode: BENPR dateStart: 20130301 isFulltext: true titleUrlDefault: https://www.proquest.com/central providerName: ProQuest – providerCode: PRVPQU databaseName: Publicly Available Content Database customDbUrl: eissn: 2227-7390 dateEnd: 99991231 omitProxy: false ssIdentifier: ssj0000913849 issn: 2227-7390 databaseCode: PIMPY dateStart: 20130301 isFulltext: true titleUrlDefault: http://search.proquest.com/publiccontent providerName: ProQuest |
| link | http://cvtisr.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwrR3LbhMx0EKlBzhUtIAItJEPRRyQ1X3YsX1Mq1Qg2nRFAJWT5de2RU2KGuDIL_DLzNi7IRwqLlx88Iwt2zM7j9U8CNkvCx8drzlTUQXGq9Ay52vPZD1SlS5BJaT0sU8ncjpV5-e6WWv1hTFhuTxwfrgD70Y8-OCECp6LaG3gUdSy1laEqEbJNCqkXnOmkgzWZa24zpHuNfj1B2D_XZbg6YNOK__SQalU_10COWmZ40dkqzMP6Tgfa5vci4sd8vB0VVt1-Zj8GtOUNcvO3JcsregfOKxtcsTVHHQSxU5n1xTsUpxFbDYDIgWMPr-gZyAt5l0aJu0bdyLg6DtYhPN4S2drqQ_0KiP19Wb7HZdPyMfjyYejN6xrq8A8aO9vzMW2iNop7kTZajC5QuVsy8s44jE1hdXC-Shs1cLTc6mAdoXj2okgnLIgEp6SjcXNIj4jVEW0IGFBKWGDWmoLS5x1qrKwkSgG5HX_0MZ3Ncex9cW1Ad8DyWLWyTIgL1fYX3OtjTvwDpFmKxyskJ0mgG9MxzfmX3wzIK-Q4ga_YziSt106AlwMK2KZsVSFkuB_VAOy2zOF6T7wpQE-Bigq--f_4zQvyAO4Gs__dnbJBtAy7pFN_wPIfDsk9w8n0-b9MPE4jO8kG2KQ6gzHnxOAN29Pm8-_ASzNCdM |
| linkProvider | Directory of Open Access Journals |
| linkToHtml | http://cvtisr.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMw1V1LT1QxFD5BNBEWvomjqF1IXJiG-2jntgtjRpRAZhhIQMOu9nUBw8zAjI_4K_wn_kbPuY8BF7hj4bY9bXrbr-d87e05B-BlmvjoRC64iipwkYWSO597XuRdlekUTULlPvZpUAyH6vBQ7y3A79YXhp5VtjqxUtRh4umOfB0bqkKRdn17ds4paxT9XW1TaNSw6MefP_DINnuz_R7Xdy3LNj8cbGzxJqsA92i8vnIXyyRqp4STaamRcYTM2VKksStilRNVS-ejtFnpkCsUCoeeOKGdDNIpizsC-70BN0WuCtpX_YLP73QoxqYSun5fn-c6WUfWeZxmSMmyNP3L8lUJAq4yA5Vt27z7v83KPbjTsGjWq2F_Hxbi-AEs78xD0M4ewq8eq5yL-a77Uit1dlGPbffqh2kjNN2MEsKdMqTvVErSfB-xHOiR_hHbRaU6arxVWZvflCo2viFxHsUp27_kIcJOaqE2LG_b4-wRfLyWGVmBxfFkHB8DU5GINjZIC-wgL7TFJs46lVnsSCYdeN0iw_gmNDtlCDk1eEQjHJnLOOrA2lz6rA5JcoXcOwLZXIYCiVcFk-mRafSS8TiS4IOTKngho7VBRJkXubYyRNW1HXhFEDWk7nBI3jZeG_hhFDjM9BB9iECkmR1YbSFqGj04Mxf4fPLv6hdwe-tgZ2AG28P-U1jCDxD1RdcqLOKKxWdwy3_HxZw-r7Ycg8_XjeY_3a1tIQ |
| linkToPdf | http://cvtisr.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMw1V1LbxMxEB6VFCE48EYECvhAxQFZ2fXaWfuAUGiJiNqmKxVQezJ-bVvUJCXhIX4F_4dfx3gfaTmUWw9c12PLa3-e-dY7D4DnaeKC5RmnMkhPOfMltS5zNM_6kqkUTUIVPvZxOx-P5f6-KlbgdxsLE90qW51YKWo_c_GOvIcdZS6jdu2VjVtEsTl8ffqFxgpS8U9rW06jhshW-PkDP98Wr0abuNfrjA3fvt94R5sKA9ShIftKbSiToKzkVqSlQvbhmTUlT0Ofh6o-qhLWBWFYaZE35BJfI7FcWeGFlQZPB457BVaRknPWgdVitFMcLG94YsZNyVXtbZ9lKukhBz1KGRI0lqZ_2cGqXMBFRqGydMNb__Ma3YabDb8mg_pA3IGVML0LN3aWyWkX9-DXgFRhx3TXfq7VPTlrx75F7bI2QaNOYqm4E4LEPj6N0nQPUe6j-_4h2UV1O2niWElb-TQ2bHxDSj0Jc7J3LnaEHNdCbcLedsTFffhwKSvyADrT2TQ8BCJDpODYIc1xgCxXBrtYYyUzOJBIuvCyRYl2TdL2WDvkROPHW8SUPo-pLqwvpU_rZCUXyL2JgFvKxBTj1YPZ_FA3Gks7nIl33grpHRfBGM-DyPJMGeGD7JsuvIhw1VER4pScaeI58MViSjE9QCQiGpGAdmGthatuNORCn2H10b-bn8E1BLHeHo23HsN1nD-vb8DWoIMbFp7AVfcd93L-tDl_BD5dNpz_ACfEd6I |
| openUrl | ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Ajournal&rft.genre=article&rft.atitle=A+Multi-Objective+Mathematical+Programming+Model+for+Project-Scheduling+Optimization+Considering+Customer+Satisfaction+in+Construction+Projects&rft.jtitle=Mathematics+%28Basel%29&rft.au=Mehrnoosh+Zohrehvandi&rft.au=Shakib+Zohrehvandi&rft.au=Mohammad+Khalilzadeh&rft.au=Maghsoud+Amiri&rft.date=2024-01-01&rft.pub=MDPI+AG&rft.eissn=2227-7390&rft.volume=12&rft.issue=2&rft.spage=211&rft_id=info:doi/10.3390%2Fmath12020211&rft.externalDBID=DOA&rft.externalDocID=oai_doaj_org_article_cb64dcdb58dc45eaad4e53739a5de86a |
| thumbnail_l | http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/lc.gif&issn=2227-7390&client=summon |
| thumbnail_m | http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/mc.gif&issn=2227-7390&client=summon |
| thumbnail_s | http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/sc.gif&issn=2227-7390&client=summon |