Effective IG heuristics for a single-machine scheduling problem with family setups and resource constraints

In this paper we investigate the problem of scheduling a set of jobs on a single-machine. The jobs are classified in families and setup times are required between the processing of two jobs of different families. Each job requires a certain amount of a common resource that is supplied through upstre...

Celý popis

Uloženo v:
Podrobná bibliografie
Vydáno v:Annals of mathematics and artificial intelligence Ročník 88; číslo 1-3; s. 169 - 185
Hlavní autoři: Pinheiro, Júlio C. S. N., Arroyo, José Elias C.
Médium: Journal Article
Jazyk:angličtina
Vydáno: Cham Springer International Publishing 01.03.2020
Springer
Springer Nature B.V
Témata:
ISSN:1012-2443, 1573-7470
On-line přístup:Získat plný text
Tagy: Přidat tag
Žádné tagy, Buďte první, kdo vytvoří štítek k tomuto záznamu!
Abstract In this paper we investigate the problem of scheduling a set of jobs on a single-machine. The jobs are classified in families and setup times are required between the processing of two jobs of different families. Each job requires a certain amount of a common resource that is supplied through upstream processes. The total resource consumed must not exceed the resource supply up. Therefore, jobs may have to wait and the machine has to be idle due to an insufficient availability of the resource. To minimize the total tardiness, simple and effective iterated greedy (IG) heuristics are proposed. Different neighborhood operators are used in the local search phase. To choose the right neighborhood operators, we propose an adaptive selecting strategy. The heuristics are tested over an extensive computational experience on benchmark of instances from the literature and instances randomly generated in this work. Experimental results and statistical tests show that the proposed heuristics are able to obtain high-quality solutions within reasonable computational effort, and they outperform the state-of-the-art heuristic.
AbstractList In this paper we investigate the problem of scheduling a set of jobs on a single-machine. The jobs are classified in families and setup times are required between the processing of two jobs of different families. Each job requires a certain amount of a common resource that is supplied through upstream processes. The total resource consumed must not exceed the resource supply up. Therefore, jobs may have to wait and the machine has to be idle due to an insufficient availability of the resource. To minimize the total tardiness, simple and effective iterated greedy (IG) heuristics are proposed. Different neighborhood operators are used in the local search phase. To choose the right neighborhood operators, we propose an adaptive selecting strategy. The heuristics are tested over an extensive computational experience on benchmark of instances from the literature and instances randomly generated in this work. Experimental results and statistical tests show that the proposed heuristics are able to obtain high-quality solutions within reasonable computational effort, and they outperform the state-of-the-art heuristic.
In this paper we investigate the problem of scheduling a set of jobs on a single-machine. The jobs are classified in families and setup times are required between the processing of two jobs of different families. Each job requires a certain amount of a common resource that is supplied through upstream processes. The total resource consumed must not exceed the resource supply up. Therefore, jobs may have to wait and the machine has to be idle due to an insufficient availability of the resource. To minimize the total tardiness, simple and effective iterated greedy (IG) heuristics are proposed. Different neighborhood operators are used in the local search phase. To choose the right neighborhood operators, we propose an adaptive selecting strategy. The heuristics are tested over an extensive computational experience on benchmark of instances from the literature and instances randomly generated in this work. Experimental results and statistical tests show that the proposed heuristics are able to obtain high-quality solutions within reasonable computational effort, and they outperform the state-of-the-art heuristic. Keywords Single machine scheduling * Family setup-times * Resource constraints * Total tardiness * Meta-heuristics. Mathematics Subject Classification (2010) 90C27 * 90B35 * 90C59
Audience Academic
Author Arroyo, José Elias C.
Pinheiro, Júlio C. S. N.
Author_xml – sequence: 1
  givenname: Júlio C. S. N.
  surname: Pinheiro
  fullname: Pinheiro, Júlio C. S. N.
  organization: Department of Computer Science, Universidade Federal de Viçosa
– sequence: 2
  givenname: José Elias C.
  orcidid: 0000-0003-3403-4770
  surname: Arroyo
  fullname: Arroyo, José Elias C.
  email: jarroyo@dpi.ufv.br
  organization: Department of Computer Science, Universidade Federal de Viçosa
BookMark eNp9kUFPHSEUhYmxifraP9AVSdfohWEGZmmMVROTbto14TGX99AZ5hUYjf--6JiYdGFYQG7Oxz33njNyHOeIhHzncM4B1EXmIJVgwHsGfSc71h2RU96qhimp4Li-gQsmpGxOyFnODwBVprtT8njtPboSnpDe3dA9LinkElymfk7U0hzibkQ2WbcPEWl2exyWsRbpIc3bESf6HMqeejuF8YVmLMshUxsHmjDPS3JI3RxzSTbEkr-SL96OGb-93xvy5-f176tbdv_r5u7q8p45CV1hCjvNB9F6OVjfCO1lK63vtr3Wg3BKeKkGCaoHu8W-sQ6dA9B-a8FpIZqh2ZAf67_V498FczEP1UusLY3ouRYgdCur6nxV7eyIJkQ_V5uungGnUF2jD7V-qbjm0EpoKiBWwKU554TeHFKYbHoxHMxrCmZNwdQUzFsKpquQ_g9yodgS5vi6lPFztFnRXPvEHaaPMT6h_gHuhJ-t
CitedBy_id crossref_primary_10_1016_j_ifacol_2021_04_140
crossref_primary_10_1109_TASE_2025_3575531
crossref_primary_10_21597_jist_935652
crossref_primary_10_25077_josi_v21_n2_p97_105_2022
crossref_primary_10_1111_itor_13232
crossref_primary_10_1016_j_cor_2021_105637
Cites_doi 10.1016/j.disopt.2008.04.001
10.1080/00207543.2014.883472
10.1016/j.cor.2011.12.017
10.1016/j.jpdc.2013.03.008
10.1016/j.ejor.2009.04.007
10.1016/j.cor.2013.01.018
10.1057/palgrave.jors.2602434
10.1016/j.ejor.2015.07.001
10.1007/s10951-011-0261-x
10.1016/j.cor.2012.07.004
10.1016/j.ejor.2005.12.009
10.1016/S0377-2217(99)00153-8
10.1080/00207540601009976
10.1287/opre.17.4.701
10.1504/IJCSM.2017.083755
10.1016/j.eswa.2008.08.033
10.1016/j.ejor.2006.06.061
10.1016/j.ijpe.2016.05.014
10.1016/j.ejor.2005.05.018
10.1016/j.ijpe.2004.10.020
10.1016/S0925-5273(02)00265-7
10.1016/j.ejor.2006.06.060
10.1016/j.ejor.2010.03.030
10.1016/j.cor.2005.07.020
10.1057/jors.1992.66
10.1287/moor.15.3.483
10.1016/S0167-5060(08)70742-8
10.1016/j.ejor.2010.05.036
10.1155/2016/9598041
10.1016/j.omega.2018.03.004
ContentType Journal Article
Copyright Springer Nature Switzerland AG 2019
COPYRIGHT 2020 Springer
Springer Nature Switzerland AG 2019.
Copyright_xml – notice: Springer Nature Switzerland AG 2019
– notice: COPYRIGHT 2020 Springer
– notice: Springer Nature Switzerland AG 2019.
DBID AAYXX
CITATION
8FE
8FG
ABJCF
AFKRA
ARAPS
AZQEC
BENPR
BGLVJ
CCPQU
DWQXO
GNUQQ
HCIFZ
JQ2
K7-
L6V
M7S
P5Z
P62
PHGZM
PHGZT
PKEHL
PQEST
PQGLB
PQQKQ
PQUKI
PRINS
PTHSS
DOI 10.1007/s10472-019-09646-6
DatabaseName CrossRef
ProQuest SciTech Collection
ProQuest Technology Collection
Materials Science & Engineering Collection
ProQuest Central UK/Ireland
Advanced Technologies & Computer Science Collection
ProQuest Central Essentials
ProQuest Central
Technology Collection
ProQuest One Community College
ProQuest Central
ProQuest Central Student
SciTech Premium Collection
ProQuest Computer Science Collection
Computer Science Database (ProQuest)
ProQuest Engineering Collection
Engineering Database
ProQuest advanced technologies & aerospace journals
ProQuest Advanced Technologies & Aerospace Collection
ProQuest Central Premium
ProQuest One Academic (New)
ProQuest One Academic Middle East (New)
ProQuest One Academic Eastern Edition (DO NOT USE)
ProQuest One Applied & Life Sciences
ProQuest One Academic (retired)
ProQuest One Academic UKI Edition
ProQuest Central China
Engineering collection
DatabaseTitle CrossRef
Computer Science Database
ProQuest Central Student
Technology Collection
ProQuest One Academic Middle East (New)
ProQuest Advanced Technologies & Aerospace Collection
ProQuest Central Essentials
ProQuest Computer Science Collection
SciTech Premium Collection
ProQuest One Community College
ProQuest Central China
ProQuest Central
ProQuest One Applied & Life Sciences
ProQuest Engineering Collection
ProQuest Central Korea
ProQuest Central (New)
Engineering Collection
Advanced Technologies & Aerospace Collection
Engineering Database
ProQuest One Academic Eastern Edition
ProQuest Technology Collection
ProQuest SciTech Collection
Advanced Technologies & Aerospace Database
ProQuest One Academic UKI Edition
Materials Science & Engineering Collection
ProQuest One Academic
ProQuest One Academic (New)
DatabaseTitleList
Computer Science Database

Database_xml – sequence: 1
  dbid: BENPR
  name: ProQuest Central Database Suite (ProQuest)
  url: https://www.proquest.com/central
  sourceTypes: Aggregation Database
DeliveryMethod fulltext_linktorsrc
Discipline Mathematics
Computer Science
EISSN 1573-7470
EndPage 185
ExternalDocumentID A718105403
10_1007_s10472_019_09646_6
GrantInformation_xml – fundername: Conselho Nacional de Desenvolvimento Científico e Tecnológico
  funderid: https://doi.org/10.13039/501100003593
GroupedDBID -4Z
-59
-5G
-BR
-EM
-Y2
-~C
.86
.DC
.VR
06D
0R~
0VY
1N0
1SB
2.D
203
23M
28-
2J2
2JN
2JY
2KG
2LR
2P1
2VQ
2~H
30V
4.4
406
408
409
40D
40E
5GY
5QI
5VS
67Z
6NX
8TC
8UJ
95-
95.
95~
96X
AAAVM
AABHQ
AACDK
AAHNG
AAIAL
AAJBT
AAJKR
AANZL
AAOBN
AARHV
AARTL
AASML
AATNV
AATVU
AAUYE
AAWCG
AAYIU
AAYQN
AAYTO
AAYZH
ABAKF
ABBBX
ABBXA
ABDZT
ABECU
ABFTD
ABFTV
ABHLI
ABHQN
ABJCF
ABJNI
ABJOX
ABKCH
ABKTR
ABMNI
ABMQK
ABNWP
ABQBU
ABQSL
ABSXP
ABTEG
ABTHY
ABTKH
ABTMW
ABULA
ABWNU
ABXPI
ACAOD
ACBXY
ACDTI
ACGFS
ACHSB
ACHXU
ACIWK
ACKNC
ACMDZ
ACMLO
ACOKC
ACOMO
ACPIV
ACSNA
ACZOJ
ADHHG
ADHIR
ADINQ
ADKNI
ADKPE
ADRFC
ADTPH
ADURQ
ADYFF
ADZKW
AEBTG
AEFIE
AEFQL
AEGAL
AEGNC
AEJHL
AEJRE
AEKMD
AEMSY
AENEX
AEOHA
AEPYU
AESKC
AETLH
AEVLU
AEXYK
AFBBN
AFEXP
AFGCZ
AFKRA
AFLOW
AFQWF
AFWTZ
AFZKB
AGAYW
AGDGC
AGGDS
AGJBK
AGMZJ
AGQEE
AGQMX
AGRTI
AGWIL
AGWZB
AGYKE
AHAVH
AHBYD
AHKAY
AHSBF
AHYZX
AIAKS
AIGIU
AIIXL
AILAN
AITGF
AJBLW
AJRNO
AJZVZ
ALMA_UNASSIGNED_HOLDINGS
ALWAN
AMKLP
AMXSW
AMYLF
AMYQR
AOCGG
ARAPS
ARMRJ
ASPBG
AVWKF
AXYYD
AYJHY
AZFZN
B-.
BA0
BBWZM
BDATZ
BENPR
BGLVJ
BGNMA
BSONS
CAG
CCPQU
COF
CS3
CSCUP
DDRTE
DL5
DNIVK
DPUIP
EBLON
EBS
EIOEI
EJD
ESBYG
F5P
FEDTE
FERAY
FFXSO
FIGPU
FINBP
FNLPD
FRRFC
FSGXE
FWDCC
GGCAI
GGRSB
GJIRD
GNWQR
GQ6
GQ7
GQ8
GXS
HCIFZ
HF~
HG5
HG6
HMJXF
HQYDN
HRMNR
HVGLF
HZ~
I09
IAO
IHE
IJ-
IKXTQ
ITM
IWAJR
IXC
IZIGR
IZQ
I~X
I~Z
J-C
J0Z
JBSCW
JCJTX
JZLTJ
K7-
KDC
KOV
KOW
LAK
LLZTM
M4Y
M7S
MA-
N2Q
NB0
NDZJH
NPVJJ
NQJWS
NU0
O9-
O93
O9G
O9I
O9J
OAM
OVD
P19
P2P
P9O
PF0
PT4
PT5
PTHSS
QOK
QOS
R4E
R89
R9I
RHV
RNI
RNS
ROL
RPX
RSV
RZC
RZE
RZK
S16
S1Z
S26
S27
S28
S3B
SAP
SCJ
SCLPG
SCO
SDH
SDM
SHX
SISQX
SJYHP
SNE
SNPRN
SNX
SOHCF
SOJ
SPISZ
SRMVM
SSLCW
STPWE
SZN
T13
T16
TEORI
TN5
TSG
TSK
TSV
TUC
U2A
UG4
UOJIU
UTJUX
UZXMN
VC2
VFIZW
W23
W48
WK8
YLTOR
Z45
Z7R
Z7X
Z81
Z83
Z88
Z92
ZMTXR
~A9
~EX
AAPKM
AAYXX
ABBRH
ABDBE
ABFSG
ABRTQ
ACSTC
ADHKG
ADKFA
AEZWR
AFDZB
AFFHD
AFHIU
AFOHR
AGQPQ
AHPBZ
AHWEU
AIXLP
ATHPR
AYFIA
CITATION
PHGZM
PHGZT
PQGLB
8FE
8FG
AZQEC
DWQXO
GNUQQ
JQ2
L6V
P62
PKEHL
PQEST
PQQKQ
PQUKI
PRINS
ID FETCH-LOGICAL-c406t-7e681d25f4daf328f454af6b988d2c72f47d40790abe93acecc008fba0c8223d3
IEDL.DBID P5Z
ISICitedReferencesCount 5
ISICitedReferencesURI http://www.webofscience.com/api/gateway?GWVersion=2&SrcApp=Summon&SrcAuth=ProQuest&DestLinkType=CitingArticles&DestApp=WOS_CPL&KeyUT=000512057700010&url=https%3A%2F%2Fcvtisr.summon.serialssolutions.com%2F%23%21%2Fsearch%3Fho%3Df%26include.ft.matches%3Dt%26l%3Dnull%26q%3D
ISSN 1012-2443
IngestDate Wed Nov 05 14:50:05 EST 2025
Sat Nov 29 10:06:55 EST 2025
Sat Nov 29 05:14:37 EST 2025
Tue Nov 18 22:22:45 EST 2025
Fri Feb 21 02:26:56 EST 2025
IsPeerReviewed true
IsScholarly true
Issue 1-3
Keywords Resource constraints
Family setup-times
90B35
90C59
90C27
Single machine scheduling
Total tardiness
Meta-heuristics
Language English
LinkModel DirectLink
MergedId FETCHMERGED-LOGICAL-c406t-7e681d25f4daf328f454af6b988d2c72f47d40790abe93acecc008fba0c8223d3
Notes ObjectType-Article-1
SourceType-Scholarly Journals-1
ObjectType-Feature-2
content type line 14
ORCID 0000-0003-3403-4770
PQID 2918202854
PQPubID 2043872
PageCount 17
ParticipantIDs proquest_journals_2918202854
gale_infotracacademiconefile_A718105403
crossref_primary_10_1007_s10472_019_09646_6
crossref_citationtrail_10_1007_s10472_019_09646_6
springer_journals_10_1007_s10472_019_09646_6
PublicationCentury 2000
PublicationDate 2020-03-01
PublicationDateYYYYMMDD 2020-03-01
PublicationDate_xml – month: 03
  year: 2020
  text: 2020-03-01
  day: 01
PublicationDecade 2020
PublicationPlace Cham
PublicationPlace_xml – name: Cham
– name: Dordrecht
PublicationTitle Annals of mathematics and artificial intelligence
PublicationTitleAbbrev Ann Math Artif Intell
PublicationYear 2020
Publisher Springer International Publishing
Springer
Springer Nature B.V
Publisher_xml – name: Springer International Publishing
– name: Springer
– name: Springer Nature B.V
References Sioud, Gravel, Gagné (CR13) 2012; 39
Herr, Goel (CR1) 2016; 248
Rodriguez, Lozano, Blum, García-Martínez (CR28) 2013; 40
Briskorn, Jaehn, Pesch (CR24) 2013; 16
Potts, Van Wassenhove (CR19) 1992; 43
Ying, Lin, Huang (CR12) 2009; 36
Tanaka, Araki (CR15) 2013; 40
Sen, Sulek, Dileepan (CR4) 2003; 83
Subramanian, Battarra, Potts (CR16) 2014; 52
Koulamas (CR3) 2010; 202
Emmons (CR5) 1969; 17
Lin, Ying (CR11) 2008; 59
Du, Leung (CR2) 1990; 15
Schaller, Gupta (CR20) 2008; 187
Allahverdi, Ng, Cheng, Kovalyov (CR7) 2008; 187
Bigras, Gamache, Savard (CR14) 2008; 5
Fanjul-Peyro, Ruiz (CR25) 2010; 207
Gupta, Smith (CR9) 2006; 175
Gupta, Chantaravarapan (CR17) 2008; 46
CR27
Liao, Juan (CR10) 2007; 34
CR21
Briskorn, Choi, Lee, Leung, Pinedo (CR23) 2010; 207
Lawler (CR6) 1977; 1
Potts, Kovalyov (CR8) 2000; 120
Schaller (CR18) 2007; 105
Ruiz, Stützle (CR26) 2007; 177
Peng, Han, Xiao, Ullah (CR22) 2017; 8
Kang, He, Wei (CR29) 2013; 73
Zhou, Liu, Chen, Li (CR30) 2016; 179
Y Peng (9646_CR22) 2017; 8
A Subramanian (9646_CR16) 2014; 52
CN Potts (9646_CR19) 1992; 43
CN Potts (9646_CR8) 2000; 120
9646_CR21
D Briskorn (9646_CR24) 2013; 16
J Schaller (9646_CR18) 2007; 105
9646_CR27
Q Kang (9646_CR29) 2013; 73
J Du (9646_CR2) 1990; 15
C Koulamas (9646_CR3) 2010; 202
FJ Rodriguez (9646_CR28) 2013; 40
SR Gupta (9646_CR9) 2006; 175
L Fanjul-Peyro (9646_CR25) 2010; 207
JN Gupta (9646_CR17) 2008; 46
A Sioud (9646_CR13) 2012; 39
H Emmons (9646_CR5) 1969; 17
C-J Liao (9646_CR10) 2007; 34
S Tanaka (9646_CR15) 2013; 40
S Lin (9646_CR11) 2008; 59
L-P Bigras (9646_CR14) 2008; 5
D Briskorn (9646_CR23) 2010; 207
S Zhou (9646_CR30) 2016; 179
JE Schaller (9646_CR20) 2008; 187
A Allahverdi (9646_CR7) 2008; 187
EL Lawler (9646_CR6) 1977; 1
K-C Ying (9646_CR12) 2009; 36
T Sen (9646_CR4) 2003; 83
O Herr (9646_CR1) 2016; 248
R Ruiz (9646_CR26) 2007; 177
References_xml – volume: 5
  start-page: 685
  issue: 4
  year: 2008
  end-page: 699
  ident: CR14
  article-title: The time-dependent traveling salesman problem and single machine scheduling problems with sequence dependent setup times
  publication-title: Discret. Optim.
  doi: 10.1016/j.disopt.2008.04.001
– volume: 52
  start-page: 2729
  issue: 9
  year: 2014
  end-page: 2742
  ident: CR16
  article-title: An iterated local search heuristic for the single machine total weighted tardiness scheduling problem with sequence-dependent setup times
  publication-title: Int. J. Prod. Res.
  doi: 10.1080/00207543.2014.883472
– volume: 39
  start-page: 2415
  issue: 10
  year: 2012
  end-page: 2424
  ident: CR13
  article-title: A hybrid genetic algorithm for the single machine scheduling problem with sequence-dependent setup times
  publication-title: Comput. Oper. Res.
  doi: 10.1016/j.cor.2011.12.017
– volume: 73
  start-page: 1106
  issue: 8
  year: 2013
  end-page: 1115
  ident: CR29
  article-title: An effective iterated greedy algorithm for reliability-oriented task allocation in distributed computing systems
  publication-title: J. Parallel Distrib. Comput.
  doi: 10.1016/j.jpdc.2013.03.008
– volume: 202
  start-page: 1
  issue: 1
  year: 2010
  end-page: 7
  ident: CR3
  article-title: The single-machine total tardiness scheduling problem: review and extensions
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2009.04.007
– volume: 40
  start-page: 1829
  issue: 7
  year: 2013
  end-page: 1841
  ident: CR28
  article-title: An iterated greedy algorithm for the large-scale unrelated parallel machines scheduling problem
  publication-title: Comput. Oper. Res.
  doi: 10.1016/j.cor.2013.01.018
– volume: 59
  start-page: 1109
  issue: 8
  year: 2008
  end-page: 1119
  ident: CR11
  article-title: A hybrid approach for single-machine tardiness problems with sequence-dependent setup times
  publication-title: J. Oper. Res. Soc.
  doi: 10.1057/palgrave.jors.2602434
– volume: 248
  start-page: 123
  issue: 1
  year: 2016
  end-page: 135
  ident: CR1
  article-title: Minimising total tardiness for a single machine scheduling problem with family setups and resource constraints
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2015.07.001
– volume: 16
  start-page: 105
  issue: 1
  year: 2013
  end-page: 115
  ident: CR24
  article-title: Exact algorithms for inventory constrained scheduling on a single machine
  publication-title: J. Sched.
  doi: 10.1007/s10951-011-0261-x
– volume: 40
  start-page: 344
  issue: 1
  year: 2013
  end-page: 352
  ident: CR15
  article-title: An exact algorithm for the single-machine total weighted tardiness problem with sequence-dependent setup times
  publication-title: Comput. Oper. Res.
  doi: 10.1016/j.cor.2012.07.004
– volume: 177
  start-page: 2033
  issue: 3
  year: 2007
  end-page: 2049
  ident: CR26
  article-title: A simple and effective iterated greedy algorithm for the permutation flowshop scheduling problem
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2005.12.009
– volume: 120
  start-page: 228
  issue: 2
  year: 2000
  end-page: 249
  ident: CR8
  article-title: Scheduling with batching: a review
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/S0377-2217(99)00153-8
– volume: 46
  start-page: 1707
  issue: 6
  year: 2008
  end-page: 1722
  ident: CR17
  article-title: Single machine group scheduling with family setups to minimize total tardiness
  publication-title: Int. J. Prod. Res.
  doi: 10.1080/00207540601009976
– volume: 17
  start-page: 701
  issue: 4
  year: 1969
  end-page: 715
  ident: CR5
  article-title: One-machine sequencing to minimize certain functions of job tardiness
  publication-title: Oper. Res.
  doi: 10.1287/opre.17.4.701
– volume: 8
  start-page: 166
  issue: 2
  year: 2017
  end-page: 174
  ident: CR22
  article-title: Heuristics for single machine scheduling problem with family setup times
  publication-title: Int. J. Comput. Sci. Math.
  doi: 10.1504/IJCSM.2017.083755
– volume: 36
  start-page: 7087
  issue: 3
  year: 2009
  end-page: 7092
  ident: CR12
  article-title: Sequencing single-machine tardiness problems with sequence dependent setup times using an iterated greedy heuristic
  publication-title: Expert Syst. Appl.
  doi: 10.1016/j.eswa.2008.08.033
– volume: 187
  start-page: 1050
  issue: 3
  year: 2008
  end-page: 1068
  ident: CR20
  article-title: Single machine scheduling with family setups to minimize total earliness and tardiness
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2006.06.061
– volume: 179
  start-page: 1
  year: 2016
  end-page: 11
  ident: CR30
  article-title: An effective discrete differential evolution algorithm for scheduling uniform parallel batch processing machines with non-identical capacities and arbitrary job sizes
  publication-title: Int. J. Prod. Econ.
  doi: 10.1016/j.ijpe.2016.05.014
– ident: CR27
– volume: 175
  start-page: 722
  issue: 2
  year: 2006
  end-page: 739
  ident: CR9
  article-title: Algorithms for single machine total tardiness scheduling with sequence dependent setups
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2005.05.018
– volume: 105
  start-page: 329
  issue: 2
  year: 2007
  end-page: 344
  ident: CR18
  article-title: Scheduling on a single machine with family setups to minimize total tardiness
  publication-title: Int. J. Prod. Econ.
  doi: 10.1016/j.ijpe.2004.10.020
– ident: CR21
– volume: 83
  start-page: 1
  issue: 1
  year: 2003
  end-page: 12
  ident: CR4
  article-title: Static scheduling research to minimize weighted and unweighted tardiness: a state-of-the-art survey
  publication-title: Int. J. Prod. Econ.
  doi: 10.1016/S0925-5273(02)00265-7
– volume: 187
  start-page: 985
  issue: 3
  year: 2008
  end-page: 1032
  ident: CR7
  article-title: A survey of scheduling problems with setup times or costs
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2006.06.060
– volume: 207
  start-page: 55
  issue: 1
  year: 2010
  end-page: 69
  ident: CR25
  article-title: Iterated greedy local search methods for unrelated parallel machine scheduling
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2010.03.030
– volume: 34
  start-page: 1899
  issue: 7
  year: 2007
  end-page: 1909
  ident: CR10
  article-title: An ant colony optimization for single-machine tardiness scheduling with sequence-dependent setups
  publication-title: Comput. Oper. Res.
  doi: 10.1016/j.cor.2005.07.020
– volume: 43
  start-page: 395
  issue: 5
  year: 1992
  end-page: 406
  ident: CR19
  article-title: Integrating scheduling with batching and lot-sizing: a review of algorithms and complexity
  publication-title: J. Oper. Res. Soc.
  doi: 10.1057/jors.1992.66
– volume: 15
  start-page: 483
  issue: 3
  year: 1990
  end-page: 495
  ident: CR2
  article-title: Minimizing total tardiness on one machine is np-hard
  publication-title: Math. Oper. Res.
  doi: 10.1287/moor.15.3.483
– volume: 1
  start-page: 331
  year: 1977
  end-page: 342
  ident: CR6
  article-title: A “pseudopolynomial” algorithm for sequencing jobs to minimize total tardiness
  publication-title: Ann. Discrete Math.
  doi: 10.1016/S0167-5060(08)70742-8
– volume: 207
  start-page: 605
  issue: 2
  year: 2010
  end-page: 619
  ident: CR23
  article-title: Complexity of single machine scheduling subject to nonnegative inventory constraints
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2010.05.036
– volume: 207
  start-page: 605
  issue: 2
  year: 2010
  ident: 9646_CR23
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2010.05.036
– volume: 73
  start-page: 1106
  issue: 8
  year: 2013
  ident: 9646_CR29
  publication-title: J. Parallel Distrib. Comput.
  doi: 10.1016/j.jpdc.2013.03.008
– volume: 52
  start-page: 2729
  issue: 9
  year: 2014
  ident: 9646_CR16
  publication-title: Int. J. Prod. Res.
  doi: 10.1080/00207543.2014.883472
– volume: 8
  start-page: 166
  issue: 2
  year: 2017
  ident: 9646_CR22
  publication-title: Int. J. Comput. Sci. Math.
  doi: 10.1504/IJCSM.2017.083755
– volume: 83
  start-page: 1
  issue: 1
  year: 2003
  ident: 9646_CR4
  publication-title: Int. J. Prod. Econ.
  doi: 10.1016/S0925-5273(02)00265-7
– volume: 120
  start-page: 228
  issue: 2
  year: 2000
  ident: 9646_CR8
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/S0377-2217(99)00153-8
– volume: 175
  start-page: 722
  issue: 2
  year: 2006
  ident: 9646_CR9
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2005.05.018
– ident: 9646_CR21
  doi: 10.1155/2016/9598041
– volume: 36
  start-page: 7087
  issue: 3
  year: 2009
  ident: 9646_CR12
  publication-title: Expert Syst. Appl.
  doi: 10.1016/j.eswa.2008.08.033
– volume: 40
  start-page: 1829
  issue: 7
  year: 2013
  ident: 9646_CR28
  publication-title: Comput. Oper. Res.
  doi: 10.1016/j.cor.2013.01.018
– volume: 39
  start-page: 2415
  issue: 10
  year: 2012
  ident: 9646_CR13
  publication-title: Comput. Oper. Res.
  doi: 10.1016/j.cor.2011.12.017
– volume: 40
  start-page: 344
  issue: 1
  year: 2013
  ident: 9646_CR15
  publication-title: Comput. Oper. Res.
  doi: 10.1016/j.cor.2012.07.004
– volume: 187
  start-page: 1050
  issue: 3
  year: 2008
  ident: 9646_CR20
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2006.06.061
– volume: 5
  start-page: 685
  issue: 4
  year: 2008
  ident: 9646_CR14
  publication-title: Discret. Optim.
  doi: 10.1016/j.disopt.2008.04.001
– volume: 59
  start-page: 1109
  issue: 8
  year: 2008
  ident: 9646_CR11
  publication-title: J. Oper. Res. Soc.
  doi: 10.1057/palgrave.jors.2602434
– volume: 16
  start-page: 105
  issue: 1
  year: 2013
  ident: 9646_CR24
  publication-title: J. Sched.
  doi: 10.1007/s10951-011-0261-x
– volume: 105
  start-page: 329
  issue: 2
  year: 2007
  ident: 9646_CR18
  publication-title: Int. J. Prod. Econ.
  doi: 10.1016/j.ijpe.2004.10.020
– volume: 17
  start-page: 701
  issue: 4
  year: 1969
  ident: 9646_CR5
  publication-title: Oper. Res.
  doi: 10.1287/opre.17.4.701
– volume: 207
  start-page: 55
  issue: 1
  year: 2010
  ident: 9646_CR25
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2010.03.030
– ident: 9646_CR27
  doi: 10.1016/j.omega.2018.03.004
– volume: 15
  start-page: 483
  issue: 3
  year: 1990
  ident: 9646_CR2
  publication-title: Math. Oper. Res.
  doi: 10.1287/moor.15.3.483
– volume: 177
  start-page: 2033
  issue: 3
  year: 2007
  ident: 9646_CR26
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2005.12.009
– volume: 202
  start-page: 1
  issue: 1
  year: 2010
  ident: 9646_CR3
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2009.04.007
– volume: 34
  start-page: 1899
  issue: 7
  year: 2007
  ident: 9646_CR10
  publication-title: Comput. Oper. Res.
  doi: 10.1016/j.cor.2005.07.020
– volume: 43
  start-page: 395
  issue: 5
  year: 1992
  ident: 9646_CR19
  publication-title: J. Oper. Res. Soc.
  doi: 10.1057/jors.1992.66
– volume: 187
  start-page: 985
  issue: 3
  year: 2008
  ident: 9646_CR7
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2006.06.060
– volume: 46
  start-page: 1707
  issue: 6
  year: 2008
  ident: 9646_CR17
  publication-title: Int. J. Prod. Res.
  doi: 10.1080/00207540601009976
– volume: 179
  start-page: 1
  year: 2016
  ident: 9646_CR30
  publication-title: Int. J. Prod. Econ.
  doi: 10.1016/j.ijpe.2016.05.014
– volume: 248
  start-page: 123
  issue: 1
  year: 2016
  ident: 9646_CR1
  publication-title: Eur. J. Oper. Res.
  doi: 10.1016/j.ejor.2015.07.001
– volume: 1
  start-page: 331
  year: 1977
  ident: 9646_CR6
  publication-title: Ann. Discrete Math.
  doi: 10.1016/S0167-5060(08)70742-8
SSID ssj0009686
Score 2.23579
Snippet In this paper we investigate the problem of scheduling a set of jobs on a single-machine. The jobs are classified in families and setup times are required...
SourceID proquest
gale
crossref
springer
SourceType Aggregation Database
Enrichment Source
Index Database
Publisher
StartPage 169
SubjectTerms Artificial Intelligence
Complex Systems
Computer Science
Heuristic
Mathematics
Operators
Scheduling
Statistical tests
SummonAdditionalLinks – databaseName: SpringerLINK Contemporary 1997-Present
  dbid: RSV
  link: http://cvtisr.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwnV1LT9wwEB7xOrQHnkVdSpEPSBzA0ib22skRVaXlAEK8xM1y_BAIWNAm29_fmazD0gKVyjm2Y9njmc-emW8AtoV2A1t5zxHtOi5VUfGiUIqXQYssln5gM98Wm9DHx8XVVXmSksLqLtq9c0m2mvpZspvUFEZAIT5KKq5mYR7NnSZZPj27nFLtqra-IxFXcTReIqXKvD7GH-bob6X8wjvaGp2DpfdNdxkWE8hk-xOpWIGZMFyFpa6AA0vneRU-Hj2RttZrcDthMkb1xw5_sOswTiTODHEts4weFe4Cv2-jLwPDWzFaKUpmZ6koDaM3XTZ5MWF1aMaPNbNDz0bJQ8AcYVEqSdHUn-Di4Pv5t5881WLgDk1-w3VQiGzzQZTeRpEXUQ6kjaoqi8LnTudRao93w7Jvq1AK61AyEF3EyvYdQhDhxTrMDR-G4TOwIjpFPHUuylI6kdusCn0VsG9EbaBjD7JuS4xLROU0uTszpVimtTW4tqZdW6N6sPvU53FC0_HP1ju004bOMI7sbEpFwPkRG5bZR4OdEZYVPdjshMGkw12bvCTWe0o97cFet_nTz2__d-P_mn-BDznd7tuIt02Ya0bj8BUW3K_mph5ttUL_G9M9-4s
  priority: 102
  providerName: Springer Nature
Title Effective IG heuristics for a single-machine scheduling problem with family setups and resource constraints
URI https://link.springer.com/article/10.1007/s10472-019-09646-6
https://www.proquest.com/docview/2918202854
Volume 88
WOSCitedRecordID wos000512057700010&url=https%3A%2F%2Fcvtisr.summon.serialssolutions.com%2F%23%21%2Fsearch%3Fho%3Df%26include.ft.matches%3Dt%26l%3Dnull%26q%3D
hasFullText 1
inHoldings 1
isFullTextHit
isPrint
journalDatabaseRights – providerCode: PRVPQU
  databaseName: Computer Science Database (ProQuest)
  customDbUrl:
  eissn: 1573-7470
  dateEnd: 20241213
  omitProxy: false
  ssIdentifier: ssj0009686
  issn: 1012-2443
  databaseCode: K7-
  dateStart: 19970301
  isFulltext: true
  titleUrlDefault: http://search.proquest.com/compscijour
  providerName: ProQuest
– providerCode: PRVPQU
  databaseName: Engineering Database
  customDbUrl:
  eissn: 1573-7470
  dateEnd: 20241213
  omitProxy: false
  ssIdentifier: ssj0009686
  issn: 1012-2443
  databaseCode: M7S
  dateStart: 19970301
  isFulltext: true
  titleUrlDefault: http://search.proquest.com
  providerName: ProQuest
– providerCode: PRVPQU
  databaseName: ProQuest advanced technologies & aerospace journals
  customDbUrl:
  eissn: 1573-7470
  dateEnd: 20241213
  omitProxy: false
  ssIdentifier: ssj0009686
  issn: 1012-2443
  databaseCode: P5Z
  dateStart: 19970301
  isFulltext: true
  titleUrlDefault: https://search.proquest.com/hightechjournals
  providerName: ProQuest
– providerCode: PRVPQU
  databaseName: ProQuest Central Database Suite (ProQuest)
  customDbUrl:
  eissn: 1573-7470
  dateEnd: 20241213
  omitProxy: false
  ssIdentifier: ssj0009686
  issn: 1012-2443
  databaseCode: BENPR
  dateStart: 19970301
  isFulltext: true
  titleUrlDefault: https://www.proquest.com/central
  providerName: ProQuest
– providerCode: PRVAVX
  databaseName: SpringerLINK Contemporary 1997-Present
  customDbUrl:
  eissn: 1573-7470
  dateEnd: 99991231
  omitProxy: false
  ssIdentifier: ssj0009686
  issn: 1012-2443
  databaseCode: RSV
  dateStart: 19970101
  isFulltext: true
  titleUrlDefault: https://link.springer.com/search?facet-content-type=%22Journal%22
  providerName: Springer Nature
link http://cvtisr.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwpV1Lb9QwEB71wQEOtBQqlpaVD0gcwGITO3ZyQi3qS4jVqgVUcbEcPwSibJdNlt_PTNbpClB74ZJLXpbGnvk8nvk-gBdCu8LW3nNEu45LVda8LJXiVdAii5UvbOY7sQk9HpeXl9UkJdyaVFbZ-8TOUftrRznyN3lFVOPU7_d29pOTahSdriYJjXXYJJYEkm6YFF9WpLuqU3okCiuOYUykppnUOic1FSVQwZCSiqs_AtPf7vmfc9Iu_Bxv_e_At-FhAp7sYDlTHsFamO7AVi_qwNIa34EHH26IXJvH8H3JbowukZ2dsK9hkYidGWJdZhklGq4C_9FVZAaGO2WMXNTgzpJQDaM8L1tmUVgT2sWsYXbq2TydGjBH-JRkKtrmCXw6Pvr47pQnfQbuEAa0XAeFaDcvovQ2iryMspA2qroqS587nUepPe4Xq5GtQyWsw9mCiCPWduQQlggvdmFjej0NT4GV0SnirnNRVtKJ3GZ1GKmA70b0EDoOIOuNY1wiL6fBXZkV7TIZ1KBBTWdQowbw6uad2ZK6486nX5LNDa1r_LKzqT0Bx0cMWeYAg3hG-FYMYL83tEkLvjErKw_gdT9VVrdv_--zu7-2B_dz2uF3VW_7sNHOF-E53HO_2m_NfAibh0fjyfkQ1t9rPqS61YthtwTwen7x-TfekAoF
linkProvider ProQuest
linkToHtml http://cvtisr.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMw1V1Nb9QwEB2VggQcKBQQCwV8AHEAi43tdZIDQhVQumq7QqJIvRnHH7SibJdNFsSf4jcykzhdAaK3HjgncZzkZeZ5PPMG4JHM3chW3nNku44rXVS8KLTmZchlFks_splvm03kk0lxcFC-W4GffS0MpVX2NrE11P7EUYz8uShJapzq_V7OvnLqGkW7q30LjQ4WO-HHd1yy1S_Gr_H7PhZi683-q22eugpwh86r4XnQyNHEKCpvoxRFVCNlo67KovDC5SKq3OMqpxzaKpTSOnxG9JOxskOHzlR6ieNegItII0TRpgq-X4r86razJElmcXSbMhXppFI9lVMSBCUoaaW5_s0R_ukO_tqXbd3d1tr_9qKuw7VErNlm9yfcgJUwXYe1vmkFSzZsHa7unQrV1jfhc6fejCafjd-yw7BIwtUMuTyzjAIpx4F_aTNOA6sR4Z5S9z-x1IiHURybdVEiVodmMauZnXo2T7sizBH_pjYcTX0LPpzLC7gNq9OTabgDrIhOkzafi6pUTgqbVWGoA14b0QLmcQBZDwbjkjg7Te7YLGWlCUAGAWRaABk9gKen18w6aZIzz35CGDNkt3BkZ1P5Bc6PFMDMJpKUjPi7HMBGDyyTDFptlqgawLMemsvD_77v3bNHewiXt_f3ds3ueLJzD64Iima0GX4bsNrMF-E-XHLfmqN6_qD91Rh8PG_I_gK74WPN
linkToPdf http://cvtisr.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwpV1Lb9QwEB6VFiE40FKKWCjUByQOYHUTex3nWAHbVrSripd6sxw_BKKE1SbL72cmcbrlKSHOsR3LnvF8Hs98A_BEFG5iK-85ol3HpdIV11opXoZCZLH0E5v5rthEMZvp8_Py7EoWfxftPjxJ9jkNxNJUt_tzH_evJL7JgkIKKNxHScXVNdiQ2VgTe_6btx9WtLuqq_VIJFYcDZlIaTO_H-MH0_TzAf3LS2lngKab_z_1LbidwCc76KXlDqyFehs2h8IOLOn5Ntw6vSRzbe7C557hGI9FdnzIPoZlIndmiHeZZeRsuAj8SxeVGRjeltF6UZI7S8VqGPl6We9JYU1ol_OG2dqzRXo5YI4wKpWqaJsdeD999e7FEU81GrhDKNDyIihEvPkkSm-jyHWUE2mjqkqtfe6KPMrC452xHNsqlMI6lBhEHbGyY4fQRHhxD9brr3W4D0xHp4i_zkVZSidym1VhrAL2jXhKFHEE2bA9xiUCc5rchVlRL9PaGlxb062tUSN4dtln3tN3_LX1U9p1Q7qNIzubUhRwfsSSZQ7QkGeEccUIdgfBMEnpG5OXxIZPKakjeD4Iwurzn__74N-a78GNs5dTc3I8e_0QbubkAOiC4nZhvV0swyO47r61n5rF404XvgML-QdZ
openUrl ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Ajournal&rft.genre=article&rft.atitle=Effective+IG+heuristics+for+a+single-machine+scheduling+problem+with+family+setups+and+resource+constraints&rft.jtitle=Annals+of+mathematics+and+artificial+intelligence&rft.au=Pinheiro%2C+Julio+C.S.N&rft.au=Arroyo%2C+Jose+Elias+C&rft.date=2020-03-01&rft.pub=Springer&rft.issn=1012-2443&rft.volume=88&rft.issue=1-3&rft.spage=169&rft_id=info:doi/10.1007%2Fs10472-019-09646-6&rft.externalDocID=A718105403
thumbnail_l http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/lc.gif&issn=1012-2443&client=summon
thumbnail_m http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/mc.gif&issn=1012-2443&client=summon
thumbnail_s http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/sc.gif&issn=1012-2443&client=summon