Two-machine flow shop scheduling with a common due date to maximize total early work

•Two-machine ow shop scheduling to maximize total early work is considered.•A dynamic programming approach running in O(n2d2) time is proposed.•A fully polynomial time approximation scheme (FPTAS) is developed.•The approximation results work for the weighted model - if a specific constraint is satis...

Full description

Saved in:
Bibliographic Details
Published in:European journal of operational research Vol. 300; no. 2; pp. 504 - 511
Main Authors: Chen, Xin, Miao, Qian, Lin, Bertrand M.T., Sterna, Malgorzata, Blazewicz, Jacek
Format: Journal Article
Language:English
Published: Elsevier B.V 16.07.2022
Subjects:
ISSN:0377-2217, 1872-6860
Online Access:Get full text