Memetic algorithm for solving flexible flow-shop scheduling problems with dynamic transport waiting times

•Developed dynamic waiting time calculation approach (DWC).•Developed machine selection heuristics.•Proposed memetic framework that integrate iterated greedy (IG) algorithm with machine selection heuristics. Flexible flow-shop scheduling with dynamic transport waiting times (FFSPDW) is a typical flo...

Celý popis

Uložené v:
Podrobná bibliografia
Vydané v:Computers & industrial engineering Ročník 139; s. 105984
Hlavní autori: Lei, Chuanjin, Zhao, Ning, Ye, Song, Wu, Xiuli
Médium: Journal Article
Jazyk:English
Vydavateľské údaje: Elsevier Ltd 01.01.2020
Predmet:
ISSN:0360-8352, 1879-0550
On-line prístup:Získať plný text
Tagy: Pridať tag
Žiadne tagy, Buďte prvý, kto otaguje tento záznam!
Abstract •Developed dynamic waiting time calculation approach (DWC).•Developed machine selection heuristics.•Proposed memetic framework that integrate iterated greedy (IG) algorithm with machine selection heuristics. Flexible flow-shop scheduling with dynamic transport waiting times (FFSPDW) is a typical flow shop scheduling problem in smart manufacturing system. In this problem, jobs need to be transported by transporters like AGV (Automated Guided Vehicle) to next stage after processing. During transportation, waiting time dynamically occurs for both jobs and transporters, and finally contributes to makespan. The waiting times are conditioned by buffer capacity, machine allocations and production sequence. In order to minimize makespan with consideration of dynamic waiting times, we proposed a waiting time calculation approach to evaluate waiting time and makespan. This approach considers two situations: infinite buffer capacity and zero buffer capacity. Further, we developed a memetic algorithm integrated with waiting time calculation approach to solve FFSPDW. Finally, we verified the algorithm parameters via analysis of variance. Computational results show that the proposed memetic algorithm is able to reach high quality solutions with short computation time. Consequently, the proposed approach is suitable for solving industrial FFSPDW problems.
AbstractList •Developed dynamic waiting time calculation approach (DWC).•Developed machine selection heuristics.•Proposed memetic framework that integrate iterated greedy (IG) algorithm with machine selection heuristics. Flexible flow-shop scheduling with dynamic transport waiting times (FFSPDW) is a typical flow shop scheduling problem in smart manufacturing system. In this problem, jobs need to be transported by transporters like AGV (Automated Guided Vehicle) to next stage after processing. During transportation, waiting time dynamically occurs for both jobs and transporters, and finally contributes to makespan. The waiting times are conditioned by buffer capacity, machine allocations and production sequence. In order to minimize makespan with consideration of dynamic waiting times, we proposed a waiting time calculation approach to evaluate waiting time and makespan. This approach considers two situations: infinite buffer capacity and zero buffer capacity. Further, we developed a memetic algorithm integrated with waiting time calculation approach to solve FFSPDW. Finally, we verified the algorithm parameters via analysis of variance. Computational results show that the proposed memetic algorithm is able to reach high quality solutions with short computation time. Consequently, the proposed approach is suitable for solving industrial FFSPDW problems.
ArticleNumber 105984
Author Ye, Song
Lei, Chuanjin
Zhao, Ning
Wu, Xiuli
Author_xml – sequence: 1
  givenname: Chuanjin
  surname: Lei
  fullname: Lei, Chuanjin
– sequence: 2
  givenname: Ning
  orcidid: 0000-0001-9720-1746
  surname: Zhao
  fullname: Zhao, Ning
  email: nickzhao@me.ustb.edu.cn
– sequence: 3
  givenname: Song
  surname: Ye
  fullname: Ye, Song
– sequence: 4
  givenname: Xiuli
  surname: Wu
  fullname: Wu, Xiuli
BookMark eNp9kM1OwzAQhC0EEm3hAbj5BRLWSfMnTqjiTyriAmfLsdetqySObNPSt8dROXHoaVea-UaamZPLwQ5IyB2DlAEr73epNJhmwJoUqhSW7ILMWF01CRQFXJIZ5CUkdV5k12Tu_Q4AlkXDZsS8Y4_BSCq6jXUmbHuqraPednszbKju8Me0HcbHHhK_tSP1covqu5vU0dmo9Z4eIkjVcRB9TApODH60LtCDMGHyBdOjvyFXWnQeb__ugnw9P32uXpP1x8vb6nGdyKypQiJlKzCHEmWps2Ur2joTdS4bxXSLgFXRqAozEE3b5pnQWBSq1CUozEqoclbnC8JOudJZ7x1qPjrTC3fkDPi0Fd_xuBWftuJQ8bhVZKp_jDRBBGOHWMZ0Z8mHE4mx0t6g4z5aBonKOJSBK2vO0L__xYnb
CitedBy_id crossref_primary_10_1016_j_cie_2022_108672
crossref_primary_10_1109_TASE_2021_3062994
crossref_primary_10_1016_j_cie_2025_110938
crossref_primary_10_1016_j_aei_2025_103195
crossref_primary_10_1080_00207543_2024_2373426
crossref_primary_10_1080_21681015_2024_2337029
crossref_primary_10_1016_j_eswa_2023_119512
crossref_primary_10_3390_sym14071424
crossref_primary_10_1016_j_ins_2023_119949
crossref_primary_10_1111_itor_13108
crossref_primary_10_1080_0305215X_2024_2437004
crossref_primary_10_1016_j_eswa_2023_120846
crossref_primary_10_1016_j_jmsy_2022_10_016
crossref_primary_10_3390_app132111896
crossref_primary_10_1016_j_cor_2025_107145
crossref_primary_10_7717_peerj_cs_2168
crossref_primary_10_1016_j_swevo_2025_102007
crossref_primary_10_1016_j_eswa_2024_125175
crossref_primary_10_1007_s10586_024_04803_x
crossref_primary_10_1016_j_ejor_2023_10_013
crossref_primary_10_3390_app15136995
crossref_primary_10_1016_j_knosys_2023_110968
crossref_primary_10_1061_JCEMD4_COENG_15909
crossref_primary_10_1016_j_cie_2024_110686
crossref_primary_10_1016_j_cie_2022_108786
crossref_primary_10_1016_j_eswa_2022_117460
crossref_primary_10_1016_j_jmsy_2024_08_007
crossref_primary_10_1016_j_aei_2024_102804
crossref_primary_10_1016_j_eswa_2023_120807
crossref_primary_10_1016_j_asoc_2024_112230
crossref_primary_10_1007_s11424_023_2491_3
crossref_primary_10_1016_j_cie_2020_106938
crossref_primary_10_1109_TASE_2023_3346446
crossref_primary_10_3390_app14198793
crossref_primary_10_1007_s12008_023_01414_5
crossref_primary_10_1016_j_asoc_2024_112689
crossref_primary_10_1016_j_cor_2024_106687
crossref_primary_10_1016_j_swevo_2025_101902
crossref_primary_10_1109_ACCESS_2021_3112742
crossref_primary_10_3390_pr11092737
crossref_primary_10_1080_0305215X_2022_2141236
crossref_primary_10_1016_j_eswa_2024_124194
crossref_primary_10_1177_03611981221143116
crossref_primary_10_1109_ACCESS_2023_3285710
Cites_doi 10.1016/j.cor.2009.11.001
10.1016/j.engappai.2016.10.013
10.1016/j.ins.2018.03.047
10.1016/j.ejor.2005.08.034
10.1080/0951192X.2016.1210231
10.1080/07408170590918290
10.1016/j.ejor.2005.12.009
10.1016/j.eswa.2008.09.063
10.1016/j.ejor.2004.06.038
10.1057/palgrave.jors.2602625
10.1016/j.cie.2016.08.006
10.1023/B:ANOR.0000030683.64615.c8
10.1016/0377-2217(94)00235-5
10.1080/07408179108963836
10.1080/0951192X.2013.874576
10.1007/s00170-007-1104-y
10.1016/j.cie.2016.11.020
10.1016/j.ejor.2009.09.024
10.15807/jorsj.24.136
10.1007/s10033-017-0108-2
10.1002/1099-1425(200101/02)4:1<3::AID-JOS57>3.0.CO;2-D
10.1051/ro:2000103
10.1287/mnsc.37.5.587
10.1016/j.ejor.2003.03.002
10.1080/002075497195948
10.1057/jors.2012.184
10.1016/j.asoc.2015.11.008
10.4028/www.scientific.net/AMM.65.574
ContentType Journal Article
Copyright 2019
Copyright_xml – notice: 2019
DBID AAYXX
CITATION
DOI 10.1016/j.cie.2019.07.041
DatabaseName CrossRef
DatabaseTitle CrossRef
DatabaseTitleList
DeliveryMethod fulltext_linktorsrc
Discipline Applied Sciences
Engineering
EISSN 1879-0550
ExternalDocumentID 10_1016_j_cie_2019_07_041
S0360835219304322
GroupedDBID --K
--M
-~X
.DC
.~1
0R~
1B1
1RT
1~.
1~5
29F
4.4
457
4G.
5GY
5VS
7-5
71M
8P~
9JN
9JO
AAAKG
AABNK
AACTN
AAEDT
AAEDW
AAFWJ
AAIAV
AAIKC
AAIKJ
AAKOC
AALRI
AAMNW
AAOAW
AAQFI
AAQXK
AARIN
AAXUO
ABAOU
ABMAC
ABUCO
ABXDB
ABYKQ
ACAZW
ACDAQ
ACGFO
ACGFS
ACNCT
ACNNM
ACRLP
ADBBV
ADEZE
ADGUI
ADMUD
ADRHT
ADTZH
AEBSH
AECPX
AEKER
AENEX
AFKWA
AFTJW
AGHFR
AGUBO
AGYEJ
AHHHB
AHJVU
AIEXJ
AIGVJ
AIKHN
AITUG
AJBFU
AJOXV
ALMA_UNASSIGNED_HOLDINGS
AMFUW
AMRAJ
APLSM
ARUGR
ASPBG
AVWKF
AXJTR
AZFZN
BJAXD
BKOJK
BKOMP
BLXMC
CS3
DU5
EBS
EFJIC
EFLBG
EJD
EO8
EO9
EP2
EP3
FDB
FEDTE
FGOYB
FIRID
FNPLU
FYGXN
G-2
G-Q
G8K
GBLVA
HAMUX
HLZ
HVGLF
HZ~
H~9
IHE
J1W
JJJVA
KOM
LX9
LY1
LY7
M41
MHUIS
MO0
MS~
N9A
O-L
O9-
OAUVE
OZT
P-8
P-9
P2P
PC.
PQQKQ
Q38
R2-
RIG
RNS
ROL
RPZ
RXW
SBC
SDF
SDG
SDP
SDS
SES
SET
SEW
SPC
SPCBC
SSB
SSD
SST
SSW
SSZ
T5K
TAE
TN5
WUQ
XPP
ZMT
~G-
9DU
AATTM
AAXKI
AAYWO
AAYXX
ABDPE
ABJNI
ABWVN
ACLOT
ACRPL
ACVFH
ADCNI
ADNMO
AEIPS
AEUPX
AFJKZ
AFPUW
AGQPQ
AIGII
AIIUN
AKBMS
AKRWK
AKYEP
ANKPU
APXCP
CITATION
EFKBS
~HD
ID FETCH-LOGICAL-c297t-ccbae306ec6f24bab82a83c9d1fbe0e759d7e20a9bb32afe55d6f60de26073183
ISICitedReferencesCount 58
ISICitedReferencesURI http://www.webofscience.com/api/gateway?GWVersion=2&SrcApp=Summon&SrcAuth=ProQuest&DestLinkType=CitingArticles&DestApp=WOS_CPL&KeyUT=000509784000057&url=https%3A%2F%2Fcvtisr.summon.serialssolutions.com%2F%23%21%2Fsearch%3Fho%3Df%26include.ft.matches%3Dt%26l%3Dnull%26q%3D
ISSN 0360-8352
IngestDate Sat Nov 29 07:18:39 EST 2025
Tue Nov 18 21:09:38 EST 2025
Fri Feb 23 02:48:54 EST 2024
IsPeerReviewed true
IsScholarly true
Keywords Flexible flow-shop scheduling
Integrated scheduling
Iterated greedy algorithm
Makespan
Dynamic waiting times
Language English
LinkModel OpenURL
MergedId FETCHMERGED-LOGICAL-c297t-ccbae306ec6f24bab82a83c9d1fbe0e759d7e20a9bb32afe55d6f60de26073183
ORCID 0000-0001-9720-1746
ParticipantIDs crossref_primary_10_1016_j_cie_2019_07_041
crossref_citationtrail_10_1016_j_cie_2019_07_041
elsevier_sciencedirect_doi_10_1016_j_cie_2019_07_041
PublicationCentury 2000
PublicationDate January 2020
2020-01-00
PublicationDateYYYYMMDD 2020-01-01
PublicationDate_xml – month: 01
  year: 2020
  text: January 2020
PublicationDecade 2020
PublicationTitle Computers & industrial engineering
PublicationYear 2020
Publisher Elsevier Ltd
Publisher_xml – name: Elsevier Ltd
References Elmi, Topaloglu (b0030) 2014; 27
Ribas, Leisten, Framiñan (b0105) 2010; 37
Ruizab (b0125) 2010; 205
Xiao, Hao, Zhang, Xu (b0155) 2002
Yuan, Soukhal, Chen, Lu (b0180) 2007; 178
Maggu, Das (b0080) 1980; 12
Ruizab (b0120) 2007; 177
Batur, Erol, Karasan (b0005) 2016; 100
Conway, Maxwell, Miller (b0025) 2003
Ying (b0175) 2009; 60
Elmi, Topaloglu (b0035) 2016; 30
Zhao, Ye, Li, Chen (b0195) 2017; 30
Brucker, Knust, Cheng, Shakhlevich (b0010) 2004; 129
Jin-Wei, Man-Zhan, Xing-Sheng (b0050) 2014; 40
Ruiz, Maroto (b0110) 2007; 169
Lee, Strusevich (b0065) 2005; 37
Maggu, Das, Kumar (b0085) 1981; 24
Shang, Lining, Ling, Kai (b0130) 2017; 60
Koç, Toptal, Sabuncuoglu (b0060) 2017; 103
Toptal, Koc, Sabuncuoglu (b0145) 2014; 65
Ling (b0070) 2003
Soukhal, Oulamara, Martineau (b0135) 2005; 161
Elmi, Topaloglu (b0040) 2017; 30
Chung-Yee, Chen (b0020) 2001; 4
Carlier, Neron, Emmanuel (b0015) 2000; 34
Stevens, Gemmill (b0140) 1997; 35
Hoogeveen, Lenstra, Veltman (b0045) 1996; 89
Kise, Shioyama, Ibaraki (b0055) 1991; 23
Yi, Xing, Wang, Dong, Vasilakos, Alavi, Wang (b0165) 2018
Lu, Gao, Li, Xiao (b0075) 2017; 57
Ruiz, Stützle (b0115) 2007; 177
Naderi, Zandieh, Khaleghi, Roshanaei (b0095) 2009; 36
Wang, Lai, Wu, Xing, Wang, Ishibuchi (b0150) 2018; 450
Xuan (b0160) 2011; 65
Matsuo, Shang, Sullivan (b0090) 1991; 37
Ying (b0170) 2008; 38
Ribas, Leisten, Framinan (b0100) 2010; 37
Zhang, Rose (b0190) 2013
Zabihzadeh, Rezaeian (b0185) 2016; 40
Ruizab (10.1016/j.cie.2019.07.041_b0120) 2007; 177
Chung-Yee (10.1016/j.cie.2019.07.041_b0020) 2001; 4
Maggu (10.1016/j.cie.2019.07.041_b0085) 1981; 24
Elmi (10.1016/j.cie.2019.07.041_b0040) 2017; 30
Toptal (10.1016/j.cie.2019.07.041_b0145) 2014; 65
Zhao (10.1016/j.cie.2019.07.041_b0195) 2017; 30
Ling (10.1016/j.cie.2019.07.041_b0070) 2003
Ruiz (10.1016/j.cie.2019.07.041_b0110) 2007; 169
Ruizab (10.1016/j.cie.2019.07.041_b0125) 2010; 205
Hoogeveen (10.1016/j.cie.2019.07.041_b0045) 1996; 89
Lu (10.1016/j.cie.2019.07.041_b0075) 2017; 57
Conway (10.1016/j.cie.2019.07.041_b0025) 2003
Ribas (10.1016/j.cie.2019.07.041_b0100) 2010; 37
Ying (10.1016/j.cie.2019.07.041_b0175) 2009; 60
Lee (10.1016/j.cie.2019.07.041_b0065) 2005; 37
Carlier (10.1016/j.cie.2019.07.041_b0015) 2000; 34
Shang (10.1016/j.cie.2019.07.041_b0130) 2017; 60
Matsuo (10.1016/j.cie.2019.07.041_b0090) 1991; 37
Maggu (10.1016/j.cie.2019.07.041_b0080) 1980; 12
Wang (10.1016/j.cie.2019.07.041_b0150) 2018; 450
Ribas (10.1016/j.cie.2019.07.041_b0105) 2010; 37
Batur (10.1016/j.cie.2019.07.041_b0005) 2016; 100
Soukhal (10.1016/j.cie.2019.07.041_b0135) 2005; 161
Xuan (10.1016/j.cie.2019.07.041_b0160) 2011; 65
Ying (10.1016/j.cie.2019.07.041_b0170) 2008; 38
Yuan (10.1016/j.cie.2019.07.041_b0180) 2007; 178
Elmi (10.1016/j.cie.2019.07.041_b0030) 2014; 27
Xiao (10.1016/j.cie.2019.07.041_b0155) 2002
Koç (10.1016/j.cie.2019.07.041_b0060) 2017; 103
Yi (10.1016/j.cie.2019.07.041_b0165) 2018
Jin-Wei (10.1016/j.cie.2019.07.041_b0050) 2014; 40
Kise (10.1016/j.cie.2019.07.041_b0055) 1991; 23
Zabihzadeh (10.1016/j.cie.2019.07.041_b0185) 2016; 40
Brucker (10.1016/j.cie.2019.07.041_b0010) 2004; 129
Elmi (10.1016/j.cie.2019.07.041_b0035) 2016; 30
Ruiz (10.1016/j.cie.2019.07.041_b0115) 2007; 177
Naderi (10.1016/j.cie.2019.07.041_b0095) 2009; 36
Zhang (10.1016/j.cie.2019.07.041_b0190) 2013
Stevens (10.1016/j.cie.2019.07.041_b0140) 1997; 35
References_xml – volume: 100
  start-page: 72
  year: 2016
  end-page: 87
  ident: b0005
  article-title: Robot move sequence determining and multiple part-type scheduling in hybrid flexible flow shop robotic cells
  publication-title: Computers & Industrial Engineering
– volume: 177
  start-page: 2033
  year: 2007
  end-page: 2049
  ident: b0115
  article-title: A simple and effective iterated greedy algorithm for the permutation flowshop scheduling problem
  publication-title: European Journal of Operational Research
– volume: 37
  start-page: 1439
  year: 2010
  end-page: 1454
  ident: b0105
  article-title: Review and classification of hybrid flow shop scheduling problems from a production system and a solutions procedure perspective
  publication-title: Computers & Operations Research
– volume: 177
  start-page: 2033
  year: 2007
  end-page: 2049
  ident: b0120
  article-title: A simple and effective iterated greedy algorithm for the permutation flowshop scheduling problem
  publication-title: European Journal of Operational Research
– volume: 36
  start-page: 9625
  year: 2009
  end-page: 9633
  ident: b0095
  article-title: An improved simulated annealing for hybrid flowshops with sequence-dependent setup and transportation times to minimize total completion time and total tardiness
  publication-title: Expert Systems with Applications
– volume: 450
  start-page: 128
  year: 2018
  end-page: 140
  ident: b0150
  article-title: Multi-clustering via evolutionary multi-objective optimization
  publication-title: Information Sciences
– start-page: 2633
  year: 2013
  end-page: 2642
  ident: b0190
  article-title: Simulation-based overhead-crane scheduling for a manufacturing plant
  publication-title: Proceedings of the 2013 winter simulation conference: Simulation: Making decisions in a complex world
– volume: 30
  start-page: 652
  year: 2017
  end-page: 662
  ident: b0195
  article-title: Effective iterated greedy algorithm for flow-shop scheduling problems with time lags
  publication-title: Chinese Journal of Mechanical Engineering
– volume: 4
  start-page: 3
  year: 2001
  end-page: 24
  ident: b0020
  article-title: Machine scheduling with transportation considerations
  publication-title: Journal of Scheduling
– year: 2003
  ident: b0070
  article-title: Shop scheduling with genetic algorithms
– volume: 178
  start-page: 918
  year: 2007
  end-page: 925
  ident: b0180
  article-title: A note on the complexity of flow shop scheduling with transportation constraints
  publication-title: European Journal of Operational Research
– volume: 60
  start-page: 810
  year: 2009
  end-page: 817
  ident: b0175
  article-title: An iterated greedy heuristic for multistage hybrid flowshop scheduling problems with multiprocessor tasks
  publication-title: Journal of the Operational Research Society
– volume: 34
  start-page: 1
  year: 2000
  end-page: 25
  ident: b0015
  article-title: An exact method for solving the multi-processor flow-shop
  publication-title: RAIRO - Operations Research
– volume: 40
  start-page: 319
  year: 2016
  end-page: 330
  ident: b0185
  article-title: Two meta-heuristic algorithms for flexible flow shop scheduling problem with robotic transportation and release time
  publication-title: Applied Soft Computing
– volume: 23
  start-page: 10
  year: 1991
  end-page: 16
  ident: b0055
  article-title: Automated two-machine flowshop scheduling: A solvable case
  publication-title: IIE Transactions
– year: 2003
  ident: b0025
  article-title: Theory of scheduling
– volume: 205
  start-page: 1
  year: 2010
  end-page: 18
  ident: b0125
  article-title: The hybrid flow shop scheduling problem
  publication-title: European Journal of Operational Research
– year: 2018
  ident: b0165
  article-title: Behavior of crossover operators in NSGA-III for large-scale optimization problems
  publication-title: Information Sciences
– volume: 37
  start-page: 725
  year: 2005
  end-page: 736
  ident: b0065
  article-title: Two-machine shop scheduling with an uncapacitated interstage transporter
  publication-title: IIE Transactions
– volume: 129
  start-page: 81
  year: 2004
  end-page: 106
  ident: b0010
  article-title: Complexity results for flow-shop and open-shop scheduling problems with transportation delays
  publication-title: Annals of Operations Research
– volume: 65
  start-page: 574
  year: 2011
  end-page: 578
  ident: b0160
  article-title: Hybrid flowshop scheduling with finite transportation capacity
  publication-title: Applied Mechanics & Materials
– volume: 38
  start-page: 348
  year: 2008
  ident: b0170
  article-title: Solving non-permutation flowshop scheduling problems by an effective iterated greedy heuristic
  publication-title: International Journal of Advanced Manufacturing Technology
– start-page: pp
  year: 2002
  ident: b0155
  article-title: Hybrid flow shop scheduling using genetic algorithms
  publication-title: World Congress on Intelligent Control & Automation
– volume: 57
  start-page: 61
  year: 2017
  end-page: 79
  ident: b0075
  article-title: A hybrid multi-objective grey wolf optimizer for dynamic scheduling in a real-world welding industry
  publication-title: Engineering Applications of Artificial Intelligence
– volume: 37
  start-page: 587
  year: 1991
  end-page: 606
  ident: b0090
  article-title: A crane scheduling problem in a computer-integrated manufacturing environment
  publication-title: Management Science
– volume: 60
  start-page: 425
  year: 2017
  ident: b0130
  article-title: Comprehensive learning pigeon-inspired optimization with tabu list
  publication-title: SCIENCE CHINA Technological Sciences
– volume: 35
  start-page: 1
  year: 1997
  end-page: 15
  ident: b0140
  article-title: Scheduling a two-machine flowshop with travel times to minimize maximum lateness
  publication-title: International Journal of Production Research
– volume: 24
  start-page: 136
  year: 1981
  end-page: 146
  ident: b0085
  article-title: On equivalent-job for job-block in 2timesn sequencing problem with transportation-times
  publication-title: Journal of the Operations Research Society of Japan
– volume: 37
  start-page: 1439
  year: 2010
  end-page: 1454
  ident: b0100
  article-title: Review and classification of hybrid flow shop scheduling problems from a production system and a solutions procedure perspective
  publication-title: Computers & Operations Research
– volume: 12
  start-page: 574
  year: 1980
  end-page: 583
  ident: b0080
  article-title: On $2times n$ sequencing problem with transportation times of jobs
  publication-title: American Journal of Industrial Medicine
– volume: 161
  start-page: 32
  year: 2005
  end-page: 41
  ident: b0135
  article-title: Complexity of flow shop scheduling problems with transportation constraints
  publication-title: European Journal of Operational Research
– volume: 65
  start-page: 180
  year: 2014
  end-page: 196
  ident: b0145
  article-title: A joint production and transportation planning problem with heterogeneous vehicles
  publication-title: Journal of the Operational Research Society
– volume: 27
  start-page: 1144
  year: 2014
  end-page: 1159
  ident: b0030
  article-title: Scheduling multiple parts in hybrid flow shop robotic cells served by a single robot
  publication-title: International Journal of Computer Integrated Manufacturing
– volume: 40
  start-page: 235
  year: 2014
  end-page: 243
  ident: b0050
  article-title: A quantum bio-parasitic genetic algorithm for solving a hybrid scheduling problem of flow shop and two-stage transportation
  publication-title: Journal of East China University of Science & Technology
– volume: 169
  start-page: 781
  year: 2007
  end-page: 800
  ident: b0110
  article-title: A genetic algorithm for hybrid flow shops with sequence dependent setup times and machine eligibility
  publication-title: European Journal of Operational Research
– volume: 30
  start-page: 805
  year: 2016
  end-page: 821
  ident: b0035
  article-title: Multi-degree cyclic flow shop robotic cell scheduling problem: Ant colony optimization
  publication-title: International Journal of Computer Integrated Manufacturing
– volume: 30
  start-page: 805
  year: 2017
  end-page: 821
  ident: b0040
  article-title: Multi-degree cyclic flow shop robotic cell scheduling problem with multiple robots
  publication-title: International Journal of Computer Integrated Manufacturing
– volume: 89
  start-page: 172
  year: 1996
  end-page: 175
  ident: b0045
  article-title: Preemptive scheduling in a two-stage multiprocessor flow shop is NP-hard
  publication-title: European Journal of Operational Research
– volume: 103
  start-page: 178
  year: 2017
  end-page: 192
  ident: b0060
  article-title: Coordination of inbound and outbound transportation schedules with the production schedule
  publication-title: Computers & Industrial Engineering
– volume: 37
  start-page: 1439
  year: 2010
  ident: 10.1016/j.cie.2019.07.041_b0105
  article-title: Review and classification of hybrid flow shop scheduling problems from a production system and a solutions procedure perspective
  publication-title: Computers & Operations Research
  doi: 10.1016/j.cor.2009.11.001
– volume: 57
  start-page: 61
  year: 2017
  ident: 10.1016/j.cie.2019.07.041_b0075
  article-title: A hybrid multi-objective grey wolf optimizer for dynamic scheduling in a real-world welding industry
  publication-title: Engineering Applications of Artificial Intelligence
  doi: 10.1016/j.engappai.2016.10.013
– volume: 450
  start-page: 128
  year: 2018
  ident: 10.1016/j.cie.2019.07.041_b0150
  article-title: Multi-clustering via evolutionary multi-objective optimization
  publication-title: Information Sciences
  doi: 10.1016/j.ins.2018.03.047
– volume: 178
  start-page: 918
  year: 2007
  ident: 10.1016/j.cie.2019.07.041_b0180
  article-title: A note on the complexity of flow shop scheduling with transportation constraints
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2005.08.034
– volume: 30
  start-page: 805
  year: 2016
  ident: 10.1016/j.cie.2019.07.041_b0035
  article-title: Multi-degree cyclic flow shop robotic cell scheduling problem: Ant colony optimization
  publication-title: International Journal of Computer Integrated Manufacturing
  doi: 10.1080/0951192X.2016.1210231
– start-page: pp
  year: 2002
  ident: 10.1016/j.cie.2019.07.041_b0155
  article-title: Hybrid flow shop scheduling using genetic algorithms
  publication-title: World Congress on Intelligent Control & Automation
– volume: 37
  start-page: 725
  year: 2005
  ident: 10.1016/j.cie.2019.07.041_b0065
  article-title: Two-machine shop scheduling with an uncapacitated interstage transporter
  publication-title: IIE Transactions
  doi: 10.1080/07408170590918290
– volume: 177
  start-page: 2033
  year: 2007
  ident: 10.1016/j.cie.2019.07.041_b0120
  article-title: A simple and effective iterated greedy algorithm for the permutation flowshop scheduling problem
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2005.12.009
– volume: 36
  start-page: 9625
  year: 2009
  ident: 10.1016/j.cie.2019.07.041_b0095
  article-title: An improved simulated annealing for hybrid flowshops with sequence-dependent setup and transportation times to minimize total completion time and total tardiness
  publication-title: Expert Systems with Applications
  doi: 10.1016/j.eswa.2008.09.063
– volume: 169
  start-page: 781
  year: 2007
  ident: 10.1016/j.cie.2019.07.041_b0110
  article-title: A genetic algorithm for hybrid flow shops with sequence dependent setup times and machine eligibility
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2004.06.038
– volume: 60
  start-page: 810
  year: 2009
  ident: 10.1016/j.cie.2019.07.041_b0175
  article-title: An iterated greedy heuristic for multistage hybrid flowshop scheduling problems with multiprocessor tasks
  publication-title: Journal of the Operational Research Society
  doi: 10.1057/palgrave.jors.2602625
– volume: 100
  start-page: 72
  year: 2016
  ident: 10.1016/j.cie.2019.07.041_b0005
  article-title: Robot move sequence determining and multiple part-type scheduling in hybrid flexible flow shop robotic cells
  publication-title: Computers & Industrial Engineering
  doi: 10.1016/j.cie.2016.08.006
– volume: 12
  start-page: 574
  year: 1980
  ident: 10.1016/j.cie.2019.07.041_b0080
  article-title: On $2times n$ sequencing problem with transportation times of jobs
  publication-title: American Journal of Industrial Medicine
– volume: 30
  start-page: 805
  year: 2017
  ident: 10.1016/j.cie.2019.07.041_b0040
  article-title: Multi-degree cyclic flow shop robotic cell scheduling problem with multiple robots
  publication-title: International Journal of Computer Integrated Manufacturing
  doi: 10.1080/0951192X.2016.1210231
– volume: 129
  start-page: 81
  year: 2004
  ident: 10.1016/j.cie.2019.07.041_b0010
  article-title: Complexity results for flow-shop and open-shop scheduling problems with transportation delays
  publication-title: Annals of Operations Research
  doi: 10.1023/B:ANOR.0000030683.64615.c8
– year: 2018
  ident: 10.1016/j.cie.2019.07.041_b0165
  article-title: Behavior of crossover operators in NSGA-III for large-scale optimization problems
  publication-title: Information Sciences
– volume: 89
  start-page: 172
  year: 1996
  ident: 10.1016/j.cie.2019.07.041_b0045
  article-title: Preemptive scheduling in a two-stage multiprocessor flow shop is NP-hard
  publication-title: European Journal of Operational Research
  doi: 10.1016/0377-2217(94)00235-5
– volume: 40
  start-page: 235
  year: 2014
  ident: 10.1016/j.cie.2019.07.041_b0050
  article-title: A quantum bio-parasitic genetic algorithm for solving a hybrid scheduling problem of flow shop and two-stage transportation
  publication-title: Journal of East China University of Science & Technology
– volume: 23
  start-page: 10
  year: 1991
  ident: 10.1016/j.cie.2019.07.041_b0055
  article-title: Automated two-machine flowshop scheduling: A solvable case
  publication-title: IIE Transactions
  doi: 10.1080/07408179108963836
– volume: 27
  start-page: 1144
  year: 2014
  ident: 10.1016/j.cie.2019.07.041_b0030
  article-title: Scheduling multiple parts in hybrid flow shop robotic cells served by a single robot
  publication-title: International Journal of Computer Integrated Manufacturing
  doi: 10.1080/0951192X.2013.874576
– year: 2003
  ident: 10.1016/j.cie.2019.07.041_b0070
– volume: 38
  start-page: 348
  year: 2008
  ident: 10.1016/j.cie.2019.07.041_b0170
  article-title: Solving non-permutation flowshop scheduling problems by an effective iterated greedy heuristic
  publication-title: International Journal of Advanced Manufacturing Technology
  doi: 10.1007/s00170-007-1104-y
– start-page: 2633
  year: 2013
  ident: 10.1016/j.cie.2019.07.041_b0190
  article-title: Simulation-based overhead-crane scheduling for a manufacturing plant
– volume: 60
  start-page: 425
  year: 2017
  ident: 10.1016/j.cie.2019.07.041_b0130
  article-title: Comprehensive learning pigeon-inspired optimization with tabu list
  publication-title: SCIENCE CHINA Technological Sciences
– volume: 103
  start-page: 178
  year: 2017
  ident: 10.1016/j.cie.2019.07.041_b0060
  article-title: Coordination of inbound and outbound transportation schedules with the production schedule
  publication-title: Computers & Industrial Engineering
  doi: 10.1016/j.cie.2016.11.020
– volume: 205
  start-page: 1
  year: 2010
  ident: 10.1016/j.cie.2019.07.041_b0125
  article-title: The hybrid flow shop scheduling problem
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2009.09.024
– volume: 24
  start-page: 136
  year: 1981
  ident: 10.1016/j.cie.2019.07.041_b0085
  article-title: On equivalent-job for job-block in 2timesn sequencing problem with transportation-times
  publication-title: Journal of the Operations Research Society of Japan
  doi: 10.15807/jorsj.24.136
– volume: 30
  start-page: 652
  year: 2017
  ident: 10.1016/j.cie.2019.07.041_b0195
  article-title: Effective iterated greedy algorithm for flow-shop scheduling problems with time lags
  publication-title: Chinese Journal of Mechanical Engineering
  doi: 10.1007/s10033-017-0108-2
– volume: 4
  start-page: 3
  year: 2001
  ident: 10.1016/j.cie.2019.07.041_b0020
  article-title: Machine scheduling with transportation considerations
  publication-title: Journal of Scheduling
  doi: 10.1002/1099-1425(200101/02)4:1<3::AID-JOS57>3.0.CO;2-D
– volume: 34
  start-page: 1
  year: 2000
  ident: 10.1016/j.cie.2019.07.041_b0015
  article-title: An exact method for solving the multi-processor flow-shop
  publication-title: RAIRO - Operations Research
  doi: 10.1051/ro:2000103
– year: 2003
  ident: 10.1016/j.cie.2019.07.041_b0025
– volume: 37
  start-page: 587
  year: 1991
  ident: 10.1016/j.cie.2019.07.041_b0090
  article-title: A crane scheduling problem in a computer-integrated manufacturing environment
  publication-title: Management Science
  doi: 10.1287/mnsc.37.5.587
– volume: 161
  start-page: 32
  year: 2005
  ident: 10.1016/j.cie.2019.07.041_b0135
  article-title: Complexity of flow shop scheduling problems with transportation constraints
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2003.03.002
– volume: 35
  start-page: 1
  year: 1997
  ident: 10.1016/j.cie.2019.07.041_b0140
  article-title: Scheduling a two-machine flowshop with travel times to minimize maximum lateness
  publication-title: International Journal of Production Research
  doi: 10.1080/002075497195948
– volume: 65
  start-page: 180
  year: 2014
  ident: 10.1016/j.cie.2019.07.041_b0145
  article-title: A joint production and transportation planning problem with heterogeneous vehicles
  publication-title: Journal of the Operational Research Society
  doi: 10.1057/jors.2012.184
– volume: 37
  start-page: 1439
  year: 2010
  ident: 10.1016/j.cie.2019.07.041_b0100
  article-title: Review and classification of hybrid flow shop scheduling problems from a production system and a solutions procedure perspective
  publication-title: Computers & Operations Research
  doi: 10.1016/j.cor.2009.11.001
– volume: 40
  start-page: 319
  year: 2016
  ident: 10.1016/j.cie.2019.07.041_b0185
  article-title: Two meta-heuristic algorithms for flexible flow shop scheduling problem with robotic transportation and release time
  publication-title: Applied Soft Computing
  doi: 10.1016/j.asoc.2015.11.008
– volume: 65
  start-page: 574
  year: 2011
  ident: 10.1016/j.cie.2019.07.041_b0160
  article-title: Hybrid flowshop scheduling with finite transportation capacity
  publication-title: Applied Mechanics & Materials
  doi: 10.4028/www.scientific.net/AMM.65.574
– volume: 177
  start-page: 2033
  year: 2007
  ident: 10.1016/j.cie.2019.07.041_b0115
  article-title: A simple and effective iterated greedy algorithm for the permutation flowshop scheduling problem
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2005.12.009
SSID ssj0004591
Score 2.5112395
Snippet •Developed dynamic waiting time calculation approach (DWC).•Developed machine selection heuristics.•Proposed memetic framework that integrate iterated greedy...
SourceID crossref
elsevier
SourceType Enrichment Source
Index Database
Publisher
StartPage 105984
SubjectTerms Dynamic waiting times
Flexible flow-shop scheduling
Integrated scheduling
Iterated greedy algorithm
Makespan
Title Memetic algorithm for solving flexible flow-shop scheduling problems with dynamic transport waiting times
URI https://dx.doi.org/10.1016/j.cie.2019.07.041
Volume 139
WOSCitedRecordID wos000509784000057&url=https%3A%2F%2Fcvtisr.summon.serialssolutions.com%2F%23%21%2Fsearch%3Fho%3Df%26include.ft.matches%3Dt%26l%3Dnull%26q%3D
hasFullText 1
inHoldings 1
isFullTextHit
isPrint
journalDatabaseRights – providerCode: PRVESC
  databaseName: Elsevier SD Freedom Collection Journals 2021
  customDbUrl:
  eissn: 1879-0550
  dateEnd: 99991231
  omitProxy: false
  ssIdentifier: ssj0004591
  issn: 0360-8352
  databaseCode: AIEXJ
  dateStart: 19950101
  isFulltext: true
  titleUrlDefault: https://www.sciencedirect.com
  providerName: Elsevier
link http://cvtisr.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwtV1Lb9QwELZWLQc4QCkgSinygRNVkNd5OD5WqKhFouJQxMIlchybzWqbrLq7be_88Y5fSVooogcuUWQljpX5NJ4Zz3yD0NtECZEzIaNKp0mUMCojTkQZZXGcclLFJkxom02wk5N8MuFfRqNfoRbmYs6aJr-64ov_KmoYA2Gb0tl7iLubFAbgHoQOVxA7XP9J8J_VmbIsrPOfLXj-0zObSQjftKEDbQgwTbWUnreX0XLaLvbBv4X9xpel2_YyvuStct3qTRsJR4C-fylq11iiKxwJJAe-OcTSQqnu-4Gonu-wz_2p3UH_WjSzugPnj6loHTb7R7-7AHnbj3xbm5FJDesdBiwoGQQsQqEWiYzhd0MJO0ojr0aN0ec6x_2m4V2wYfYeNJ9JzOOWetVxZ91k0761y3W5hyGtbVbAFIWZoiCsIIb8YJOylINq3Dw4Ppx8GpDOu8aLYd3hcNymCd5ax5_Nm4HJcrqFHntfAx84jDxFI9Vsoyfe78Beqy-30aMBKeUzVHsA4Q5AGACEPYBwABDuAIR7AOEAIGwAhD2AcAcg7AGELYCeo68fD08_HEW-IUckKWerSMpSKPAxlcw0TUpR5lTkseTVWJeKKPh5FVOUCF6WMRVapWmV6YxUCpxmZjaPF2ijaRv1EuGxjonMqrFSlCWp0mClg7HIU6oyQ19U7iAS_iPIyWWlmKYp8-JO-e2gd90rC0fV8reHkyCcwtuazoYsAGh3v_bqPt_YRQ97_L9GG6vztdpDD-TFql6ev_EouwZ786PO
linkProvider Elsevier
openUrl ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Ajournal&rft.genre=article&rft.atitle=Memetic+algorithm+for+solving+flexible+flow-shop+scheduling+problems+with+dynamic+transport+waiting+times&rft.jtitle=Computers+%26+industrial+engineering&rft.au=Lei%2C+Chuanjin&rft.au=Zhao%2C+Ning&rft.au=Ye%2C+Song&rft.au=Wu%2C+Xiuli&rft.date=2020-01-01&rft.issn=0360-8352&rft.volume=139&rft.spage=105984&rft_id=info:doi/10.1016%2Fj.cie.2019.07.041&rft.externalDBID=n%2Fa&rft.externalDocID=10_1016_j_cie_2019_07_041
thumbnail_l http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/lc.gif&issn=0360-8352&client=summon
thumbnail_m http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/mc.gif&issn=0360-8352&client=summon
thumbnail_s http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/sc.gif&issn=0360-8352&client=summon