An efficient polynomial-time approximation scheme for parallel multi-stage open shops

Various new scheduling problems have been arising from real-world applications and spawning new research areas in the scheduling field. We study the parallel multi-stage open shops problem, which generalizes the classic open shop scheduling and parallel machine scheduling problems. Given m identical...

Full description

Saved in:
Bibliographic Details
Published in:Discrete Applied Mathematics Vol. 377; pp. 390 - 401
Main Authors: Dong, Jianming, Jin, Ruyan, Lin, Guohui, Su, Bing, Tong, Weitian, Xu, Yao
Format: Journal Article
Language:English
Published: Elsevier B.V 31.12.2025
Subjects:
ISSN:0166-218X
Online Access:Get full text
Tags: Add Tag
No Tags, Be the first to tag this record!
Abstract Various new scheduling problems have been arising from real-world applications and spawning new research areas in the scheduling field. We study the parallel multi-stage open shops problem, which generalizes the classic open shop scheduling and parallel machine scheduling problems. Given m identical k-stage open shops and a set of n jobs, we aim to process all jobs on these open shops with the minimum makespan, i.e., the completion time of the last job, under the constraint that job preemption is not allowed. We present an efficient polynomial-time approximation scheme (EPTAS) for the case when both m and k are constant. The main idea for our EPTAS is the combination of several categorization, scaling, and linear programming rounding techniques. Jobs and/or operations are first scaled and then categorized carefully into multiple types so that different types of jobs and/or operations are scheduled appropriately without increasing the makespan too much. •Proposed first EPTAS for parallel multi-stage open shops scheduling.•Combined categorization, scaling, and linear programming rounding methods.•Demonstrated effective gap-filling strategy for small job scheduling.•Achieved near-optimal makespan within polynomial runtime complexity.
AbstractList Various new scheduling problems have been arising from real-world applications and spawning new research areas in the scheduling field. We study the parallel multi-stage open shops problem, which generalizes the classic open shop scheduling and parallel machine scheduling problems. Given m identical k-stage open shops and a set of n jobs, we aim to process all jobs on these open shops with the minimum makespan, i.e., the completion time of the last job, under the constraint that job preemption is not allowed. We present an efficient polynomial-time approximation scheme (EPTAS) for the case when both m and k are constant. The main idea for our EPTAS is the combination of several categorization, scaling, and linear programming rounding techniques. Jobs and/or operations are first scaled and then categorized carefully into multiple types so that different types of jobs and/or operations are scheduled appropriately without increasing the makespan too much. •Proposed first EPTAS for parallel multi-stage open shops scheduling.•Combined categorization, scaling, and linear programming rounding methods.•Demonstrated effective gap-filling strategy for small job scheduling.•Achieved near-optimal makespan within polynomial runtime complexity.
Author Tong, Weitian
Xu, Yao
Lin, Guohui
Su, Bing
Dong, Jianming
Jin, Ruyan
Author_xml – sequence: 1
  givenname: Jianming
  surname: Dong
  fullname: Dong, Jianming
  email: djm226@163.com
  organization: School of Management and E-Business, Contemporary Business and Trade Research Center, Zhejiang Gongshang University, Hangzhou, Zhejiang, 310018, China
– sequence: 2
  givenname: Ruyan
  surname: Jin
  fullname: Jin, Ruyan
  email: jry623@163.com
  organization: Public Course Teaching and Research Office, Taizhou Vocational and Technical College, Taizhou, Zhejiang, 318000, China
– sequence: 3
  givenname: Guohui
  surname: Lin
  fullname: Lin, Guohui
  email: guohui@alberta.ca
  organization: Department of Computing Science, University of Alberta, Edmonton, Alberta, Canada, T6G 2E8
– sequence: 4
  givenname: Bing
  surname: Su
  fullname: Su, Bing
  email: subing684@sohu.com
  organization: School of Economics and Management, Xi’an Technological University, Xi’an, China
– sequence: 5
  givenname: Weitian
  orcidid: 0000-0002-9815-2330
  surname: Tong
  fullname: Tong, Weitian
  email: wtong.research@gmail.com
  organization: Department of Computer Science, Georgia Southern University, Statesboro, GA, 30458, USA
– sequence: 6
  givenname: Yao
  surname: Xu
  fullname: Xu, Yao
  email: yxu@georgiasouthern.edu
  organization: Department of Computer Science, Georgia Southern University, Statesboro, GA, 30458, USA
BookMark eNp9kM1qwzAQhHVIoUnaB-hNL2BX8o9s01MI_YNALw30JhRp1cjIlpDU0rx9FdJzT8sOM8vst0KL2c2A0B0lJSWU3Y-lElNZkaotSV8S0izQMuusqGj_cY1WMY6EEJq3JdpvZgxaG2lgTtg7e5rdZIQtkpkAC--D-zGTSMbNOMojZFG7gL0IwlqwePqyyRQxiU_AzkM2HZ2PN-hKCxvh9m-u0f7p8X37Uuzenl-3m10hq5amgg1KKjWImg0NYbRRtK8HRgRp2pZ1UEnd075jUB8qYJ3Q2Qay7g5dp9gg26FeI3q5K4OLMYDmPuS24cQp4WcWfOSZBT-z4KTnmUXOPFwykIt9Gwg8np-XoEwAmbhy5p_0Ly-ma_M
Cites_doi 10.1007/3-540-46541-3_38
10.1007/s10479-015-1934-1
10.1016/S0167-6377(99)00005-X
10.1016/j.ejor.2025.01.034
10.1016/j.cor.2015.10.012
10.1016/j.ipl.2013.01.009
10.1016/j.tcs.2016.04.046
10.1007/BF01585871
10.1080/0020754031000106443
10.1016/j.tcs.2017.09.018
10.1016/j.ejor.2019.08.019
10.1080/07408179608966258
10.1016/j.robot.2020.103560
10.1057/jors.1994.99
10.1145/321978.321985
10.1016/j.ejor.2021.03.026
10.1016/j.ejor.2011.08.007
10.1080/07408170008967427
10.1007/s10479-024-05860-6
10.1057/s41278-019-00122-w
10.1016/j.tcs.2019.01.017
10.1007/s10878-018-0314-6
10.1007/BF01585870
10.1287/opre.45.2.288
10.1016/j.tcs.2018.04.005
10.1145/321921.321934
10.1007/s10878-020-00591-3
10.1016/j.tcs.2019.08.028
10.1007/s10845-015-1149-y
10.1016/0377-2217(93)90249-M
10.1016/j.tcs.2018.04.017
10.1287/msom.2016.0591
10.1002/j.1538-7305.1966.tb01709.x
10.1145/7531.7535
10.1016/j.cor.2022.105732
ContentType Journal Article
Copyright 2025 Elsevier B.V.
Copyright_xml – notice: 2025 Elsevier B.V.
DBID AAYXX
CITATION
DOI 10.1016/j.dam.2025.08.004
DatabaseName CrossRef
DatabaseTitle CrossRef
DatabaseTitleList
DeliveryMethod fulltext_linktorsrc
Discipline Mathematics
EndPage 401
ExternalDocumentID 10_1016_j_dam_2025_08_004
S0166218X25004500
GroupedDBID -~X
ADEZE
AFTJW
ALMA_UNASSIGNED_HOLDINGS
FDB
OAUVE
AAYXX
AI.
CITATION
FA8
VH1
WUQ
ID FETCH-LOGICAL-c251t-69dcdd9a36940614d183960a045567e2cf81876e3b2e67af694ec37b77d69c593
ISICitedReferencesCount 0
ISICitedReferencesURI http://www.webofscience.com/api/gateway?GWVersion=2&SrcApp=Summon&SrcAuth=ProQuest&DestLinkType=CitingArticles&DestApp=WOS_CPL&KeyUT=001558940100001&url=https%3A%2F%2Fcvtisr.summon.serialssolutions.com%2F%23%21%2Fsearch%3Fho%3Df%26include.ft.matches%3Dt%26l%3Dnull%26q%3D
ISSN 0166-218X
IngestDate Wed Nov 05 20:52:36 EST 2025
Sat Oct 11 16:52:43 EDT 2025
IsPeerReviewed true
IsScholarly true
Keywords Linear programming
Scheduling
Makespan
Efficient polynomial-time approximation scheme
Parallel multi-stage open shops
Language English
LinkModel OpenURL
MergedId FETCHMERGED-LOGICAL-c251t-69dcdd9a36940614d183960a045567e2cf81876e3b2e67af694ec37b77d69c593
ORCID 0000-0002-9815-2330
PageCount 12
ParticipantIDs crossref_primary_10_1016_j_dam_2025_08_004
elsevier_sciencedirect_doi_10_1016_j_dam_2025_08_004
PublicationCentury 2000
PublicationDate 2025-12-31
PublicationDateYYYYMMDD 2025-12-31
PublicationDate_xml – month: 12
  year: 2025
  text: 2025-12-31
  day: 31
PublicationDecade 2020
PublicationTitle Discrete Applied Mathematics
PublicationYear 2025
Publisher Elsevier B.V
Publisher_xml – name: Elsevier B.V
References Dong, Tong, Luo, Wang, Hu, Xu, Lin (b15) 2017; 657
Hochbaum, Shmoys (b24) 1987; 34
Adak, Arıoğlu Akan, Bulkan (b1) 2020; 40
Al-Salem (b4) 2004; 2
Gong, Lin, Miyano, Su, Tong (b17) 2024; 335
Mokotoff (b28) 2001; 18
Wang, Chen, Wang (b36) 2020; 131
Wu, Chen, Wang (b42) 2020; 818
Williamson, Hall, Hoogeveen, Hurkens, Lenstra, Sevast’janov, Shmoys (b37) 1997; 45
Zhao, Chien, Gen (b44) 2018; 29
Tong, Miyano, Goebel, Lin (b34) 2018; 734
Sevastianov, Woeginger (b32) 1998; 82
Graham, Lawler, Lenstra, Kan (b20) 1979; vol. 5
Cao, Chen (b9) 2003; 41
Chen, Strusevich (b10) 1993; 70
Grinshpoun, Ilani, Shufan (b21) 2017; 252
Anand, Panneerselvam (b5) 2015; 7
Klaus Jansen, Maxim I. Sviridenko, Polynomial time approximation schemes for the multiprocessor open and flow shop scheduling problem, in: Annual Symposium on Theoretical Aspects of Computer Science, 2000, pp. 455–465.
Zhang, van de Velde (b43) 2012; 216
Kubiak (b27) 2022
Wu, Chen, Wang (b39) 2019; 786
Schuurman, Woeginger (b31) 1999; 24
Baron, Berman, Krass, Wang (b7) 2017; 19
Wu, Chen, Wang (b41) 2020; 806
Ahmadian, Khatami, Salehipour, Cheng (b3) 2021; 295
Hall (b22) 1998; 82
Agnetis, Billaut, Pinedo, Shabtay (b2) 2025
Bai, Zhang, Zhang (b6) 2016; 67
Garey, Johnson (b16) 1979; vol. 174
Prins (b29) 1994; 45
Kovalyov (b26) 1985
Cankaya, Wari, Eren Tokgoz (b8) 2019; 21
Chen, Zhang, Chen, Dong (b11) 2013; 113
He, Kusiak, Artiba (b23) 1996; 28
Vairaktarakis, Elhafsi (b35) 2000; 32
Dong, Jin, Luo, Tong (b14) 2020; 281
Graham (b19) 1966; 45
Strusevich (b33) 2022
Gerhard J. Woeginger, The open shop scheduling problem, in: 35th Symposium on Theoretical Aspects of Computer Science, STACS 2018, 2018.
Gonzalez, Sahni (b18) 1976; 23
Wu, Chen, Wang (b40) 2019; 776
Dong, Jin, Hu, Lin (b13) 2019; 37
Oliver G. Czibula, Hanyu Gu, Yakov Zinder, Timetabling of workplace training: a combination of mathematical programming and simulated annealing, in: Proceedings of the 11th International Conference on Practice and Theory of Automated Timetabling, PATAT’16, 2016, pp. 95–107.
Sahni (b30) 1976; 23
Zhang (10.1016/j.dam.2025.08.004_b43) 2012; 216
Graham (10.1016/j.dam.2025.08.004_b20) 1979; vol. 5
Wang (10.1016/j.dam.2025.08.004_b36) 2020; 131
Sevastianov (10.1016/j.dam.2025.08.004_b32) 1998; 82
Ahmadian (10.1016/j.dam.2025.08.004_b3) 2021; 295
10.1016/j.dam.2025.08.004_b25
Strusevich (10.1016/j.dam.2025.08.004_b33) 2022
Al-Salem (10.1016/j.dam.2025.08.004_b4) 2004; 2
Cao (10.1016/j.dam.2025.08.004_b9) 2003; 41
Chen (10.1016/j.dam.2025.08.004_b10) 1993; 70
Hall (10.1016/j.dam.2025.08.004_b22) 1998; 82
Tong (10.1016/j.dam.2025.08.004_b34) 2018; 734
Chen (10.1016/j.dam.2025.08.004_b11) 2013; 113
Graham (10.1016/j.dam.2025.08.004_b19) 1966; 45
Zhao (10.1016/j.dam.2025.08.004_b44) 2018; 29
Vairaktarakis (10.1016/j.dam.2025.08.004_b35) 2000; 32
Grinshpoun (10.1016/j.dam.2025.08.004_b21) 2017; 252
Prins (10.1016/j.dam.2025.08.004_b29) 1994; 45
Bai (10.1016/j.dam.2025.08.004_b6) 2016; 67
Hochbaum (10.1016/j.dam.2025.08.004_b24) 1987; 34
Gonzalez (10.1016/j.dam.2025.08.004_b18) 1976; 23
Sahni (10.1016/j.dam.2025.08.004_b30) 1976; 23
Schuurman (10.1016/j.dam.2025.08.004_b31) 1999; 24
Wu (10.1016/j.dam.2025.08.004_b39) 2019; 786
Garey (10.1016/j.dam.2025.08.004_b16) 1979; vol. 174
10.1016/j.dam.2025.08.004_b38
Kovalyov (10.1016/j.dam.2025.08.004_b26) 1985
Baron (10.1016/j.dam.2025.08.004_b7) 2017; 19
Dong (10.1016/j.dam.2025.08.004_b14) 2020; 281
Kubiak (10.1016/j.dam.2025.08.004_b27) 2022
10.1016/j.dam.2025.08.004_b12
Agnetis (10.1016/j.dam.2025.08.004_b2) 2025
Adak (10.1016/j.dam.2025.08.004_b1) 2020; 40
Wu (10.1016/j.dam.2025.08.004_b40) 2019; 776
Wu (10.1016/j.dam.2025.08.004_b42) 2020; 818
Dong (10.1016/j.dam.2025.08.004_b13) 2019; 37
Gong (10.1016/j.dam.2025.08.004_b17) 2024; 335
Mokotoff (10.1016/j.dam.2025.08.004_b28) 2001; 18
Williamson (10.1016/j.dam.2025.08.004_b37) 1997; 45
Cankaya (10.1016/j.dam.2025.08.004_b8) 2019; 21
Wu (10.1016/j.dam.2025.08.004_b41) 2020; 806
Dong (10.1016/j.dam.2025.08.004_b15) 2017; 657
He (10.1016/j.dam.2025.08.004_b23) 1996; 28
Anand (10.1016/j.dam.2025.08.004_b5) 2015; 7
References_xml – year: 2025
  ident: b2
  article-title: Fifty years of research in scheduling — Theory and applications
  publication-title: European J. Oper. Res.
– volume: 113
  start-page: 220
  year: 2013
  end-page: 224
  ident: b11
  article-title: Approximation algorithms for parallel open shop scheduling
  publication-title: Inform. Process. Lett.
– volume: 818
  start-page: 74
  year: 2020
  end-page: 82
  ident: b42
  article-title: On scheduling multiple two-stage flowshops
  publication-title: Theoret. Comput. Sci.
– reference: Gerhard J. Woeginger, The open shop scheduling problem, in: 35th Symposium on Theoretical Aspects of Computer Science, STACS 2018, 2018.
– volume: 19
  start-page: 52
  year: 2017
  end-page: 71
  ident: b7
  article-title: Strategic idleness and dynamic scheduling in an open-shop service network: Case study and analysis
  publication-title: Manuf. Serv. Oper. Manag.
– volume: 734
  start-page: 24
  year: 2018
  end-page: 31
  ident: b34
  article-title: An approximation scheme for minimizing the makespan of the parallel identical multi-stage flow-shops
  publication-title: Theoret. Comput. Sci.
– volume: 45
  start-page: 1563
  year: 1966
  end-page: 1581
  ident: b19
  article-title: Bounds for certain multiprocessing anomalies
  publication-title: Bell Syst. Tech. J.
– volume: 34
  start-page: 144
  year: 1987
  end-page: 162
  ident: b24
  article-title: Using dual approximation algorithms for scheduling problems theoretical and practical results
  publication-title: J. ACM
– volume: 70
  start-page: 379
  year: 1993
  end-page: 390
  ident: b10
  article-title: Worst-case analysis of heuristics for open shops with parallel machines
  publication-title: European J. Oper. Res.
– year: 1985
  ident: b26
  article-title: Efficient epsilon-approximation algorithm for minimizing the makespan in a parallel two-stage system
  publication-title: Vesti Acad. Navuk Belarus. SSR. Ser. Phizika- Mat. Navuk
– volume: 216
  start-page: 544
  year: 2012
  end-page: 552
  ident: b43
  article-title: Approximation algorithms for the parallel flow shop problem
  publication-title: European J. Oper. Res.
– volume: 37
  start-page: 668
  year: 2019
  end-page: 684
  ident: b13
  article-title: A fully polynomial time approximation scheme for scheduling on parallel identical two-stage openshops
  publication-title: J. Comb. Optim.
– volume: 252
  start-page: 455
  year: 2017
  end-page: 469
  ident: b21
  article-title: The representation of partially-concurrent open shop problems
  publication-title: Ann. Oper. Res.
– volume: 40
  start-page: 547
  year: 2020
  end-page: 569
  ident: b1
  article-title: Multiprocessor open shop problem: literature review and future directions
  publication-title: J. Comb. Optim.
– volume: 23
  start-page: 665
  year: 1976
  end-page: 679
  ident: b18
  article-title: Open shop scheduling to minimize finish time
  publication-title: J. ACM
– volume: 82
  start-page: 175
  year: 1998
  end-page: 190
  ident: b22
  article-title: Approximability of flow shop scheduling
  publication-title: Math. Program.
– volume: vol. 174
  year: 1979
  ident: b16
  publication-title: Computers and Intractability
– year: 2022
  ident: b27
  article-title: A book of open shop scheduling
  publication-title: Int. Ser. Oper. Res. Manag. Sci.
– volume: 18
  start-page: 193
  year: 2001
  ident: b28
  article-title: Parallel machine scheduling problems: A survey
  publication-title: Asia-Pac. J. Oper. Res.
– reference: Oliver G. Czibula, Hanyu Gu, Yakov Zinder, Timetabling of workplace training: a combination of mathematical programming and simulated annealing, in: Proceedings of the 11th International Conference on Practice and Theory of Automated Timetabling, PATAT’16, 2016, pp. 95–107.
– volume: 23
  start-page: 116
  year: 1976
  end-page: 127
  ident: b30
  article-title: Algorithms for scheduling independent tasks
  publication-title: J. ACM
– year: 2022
  ident: b33
  article-title: Complexity and approximation of open shop scheduling to minimize the makespan: A review of models and approaches
  publication-title: Comput. Oper. Res.
– volume: 131
  year: 2020
  ident: b36
  article-title: Coupled task scheduling for heterogeneous multi-robot system of two robot types performing complex-schedule order fulfillment tasks
  publication-title: Robot. Auton. Syst.
– volume: 776
  start-page: 117
  year: 2019
  end-page: 124
  ident: b40
  article-title: Scheduling two-stage jobs on multiple flowshops
  publication-title: Theoret. Comput. Sci.
– volume: vol. 5
  start-page: 287
  year: 1979
  end-page: 326
  ident: b20
  article-title: Optimization and approximation in deterministic sequencing and scheduling: a survey
  publication-title: Annals of Discrete Mathematics
– volume: 657
  start-page: 64
  year: 2017
  end-page: 72
  ident: b15
  article-title: An FPTAS for the parallel two-stage flowshop problem
  publication-title: Theoret. Comput. Sci.
– volume: 32
  start-page: 687
  year: 2000
  end-page: 699
  ident: b35
  article-title: The use of flowlines to simplify routing complexity in two-stage flowshops
  publication-title: Iie Trans.
– volume: 7
  start-page: 33
  year: 2015
  ident: b5
  article-title: Literature review of open shop scheduling problems
  publication-title: Intell. Inf. Manag.
– volume: 82
  start-page: 191
  year: 1998
  end-page: 198
  ident: b32
  article-title: Makespan minimization in open shops: A polynomial time approximation scheme
  publication-title: Math. Program.
– volume: 2
  start-page: 98
  year: 2004
  ident: b4
  article-title: A heuristic to minimize makespan in proportional parallel flow shops
  publication-title: Int. J. Comput. Inf. Sci.
– volume: 41
  start-page: 3059
  year: 2003
  end-page: 3073
  ident: b9
  article-title: Parallel flowshop scheduling using Tabu search
  publication-title: Int. J. Prod. Res.
– volume: 45
  start-page: 611
  year: 1994
  end-page: 623
  ident: b29
  article-title: An overview of scheduling problems arising in satellite communications
  publication-title: J. Oper. Res. Soc.
– volume: 786
  start-page: 67
  year: 2019
  end-page: 77
  ident: b39
  article-title: On scheduling inclined jobs on multiple two-stage flowshops
  publication-title: Theoret. Comput. Sci.
– volume: 29
  start-page: 973
  year: 2018
  end-page: 988
  ident: b44
  article-title: A bi-objective genetic algorithm for intelligent rehabilitation scheduling considering therapy precedence constraints
  publication-title: J. Intell. Manuf.
– volume: 295
  start-page: 399
  year: 2021
  end-page: 426
  ident: b3
  article-title: Four decades of research on the open-shop scheduling problem to minimize the makespan
  publication-title: European J. Oper. Res.
– volume: 67
  start-page: 207
  year: 2016
  end-page: 215
  ident: b6
  article-title: Flexible open shop scheduling problem to minimize makespan
  publication-title: Comput. Oper. Res.
– volume: 24
  start-page: 157
  year: 1999
  end-page: 163
  ident: b31
  article-title: Approximation algorithms for the multiprocessor open shop scheduling problem
  publication-title: Oper. Res. Lett.
– volume: 806
  start-page: 509
  year: 2020
  end-page: 515
  ident: b41
  article-title: Improved approximation algorithms for two-stage flowshops scheduling problem
  publication-title: Theoret. Comput. Sci.
– volume: 281
  start-page: 16
  year: 2020
  end-page: 24
  ident: b14
  article-title: A polynomial-time approximation scheme for an arbitrary number of parallel two-stage flow-shops
  publication-title: European J. Oper. Res.
– volume: 21
  start-page: 559
  year: 2019
  end-page: 575
  ident: b8
  article-title: Practical approaches to chemical tanker scheduling in ports: a case study on the Port of Houston
  publication-title: Marit. Econ. Logist.
– volume: 335
  start-page: 185
  year: 2024
  end-page: 204
  ident: b17
  article-title: A polynomial-time approximation scheme for an arbitrary number of parallel identical multi-stage flow-shops
  publication-title: Ann. Oper. Res.
– reference: Klaus Jansen, Maxim I. Sviridenko, Polynomial time approximation schemes for the multiprocessor open and flow shop scheduling problem, in: Annual Symposium on Theoretical Aspects of Computer Science, 2000, pp. 455–465.
– volume: 45
  start-page: 288
  year: 1997
  end-page: 294
  ident: b37
  article-title: Short shop schedules
  publication-title: Oper. Res.
– volume: 28
  start-page: 129
  year: 1996
  end-page: 139
  ident: b23
  article-title: A scheduling problem in glass manufacturing
  publication-title: IIE Trans.
– ident: 10.1016/j.dam.2025.08.004_b25
  doi: 10.1007/3-540-46541-3_38
– volume: 252
  start-page: 455
  issue: 2
  year: 2017
  ident: 10.1016/j.dam.2025.08.004_b21
  article-title: The representation of partially-concurrent open shop problems
  publication-title: Ann. Oper. Res.
  doi: 10.1007/s10479-015-1934-1
– volume: 18
  start-page: 193
  issue: 2
  year: 2001
  ident: 10.1016/j.dam.2025.08.004_b28
  article-title: Parallel machine scheduling problems: A survey
  publication-title: Asia-Pac. J. Oper. Res.
– volume: 24
  start-page: 157
  issue: 4
  year: 1999
  ident: 10.1016/j.dam.2025.08.004_b31
  article-title: Approximation algorithms for the multiprocessor open shop scheduling problem
  publication-title: Oper. Res. Lett.
  doi: 10.1016/S0167-6377(99)00005-X
– year: 2025
  ident: 10.1016/j.dam.2025.08.004_b2
  article-title: Fifty years of research in scheduling — Theory and applications
  publication-title: European J. Oper. Res.
  doi: 10.1016/j.ejor.2025.01.034
– volume: 67
  start-page: 207
  year: 2016
  ident: 10.1016/j.dam.2025.08.004_b6
  article-title: Flexible open shop scheduling problem to minimize makespan
  publication-title: Comput. Oper. Res.
  doi: 10.1016/j.cor.2015.10.012
– volume: 113
  start-page: 220
  issue: 7
  year: 2013
  ident: 10.1016/j.dam.2025.08.004_b11
  article-title: Approximation algorithms for parallel open shop scheduling
  publication-title: Inform. Process. Lett.
  doi: 10.1016/j.ipl.2013.01.009
– volume: 657
  start-page: 64
  year: 2017
  ident: 10.1016/j.dam.2025.08.004_b15
  article-title: An FPTAS for the parallel two-stage flowshop problem
  publication-title: Theoret. Comput. Sci.
  doi: 10.1016/j.tcs.2016.04.046
– volume: 82
  start-page: 191
  issue: 1
  year: 1998
  ident: 10.1016/j.dam.2025.08.004_b32
  article-title: Makespan minimization in open shops: A polynomial time approximation scheme
  publication-title: Math. Program.
  doi: 10.1007/BF01585871
– year: 1985
  ident: 10.1016/j.dam.2025.08.004_b26
  article-title: Efficient epsilon-approximation algorithm for minimizing the makespan in a parallel two-stage system
  publication-title: Vesti Acad. Navuk Belarus. SSR. Ser. Phizika- Mat. Navuk
– volume: 2
  start-page: 98
  issue: 2
  year: 2004
  ident: 10.1016/j.dam.2025.08.004_b4
  article-title: A heuristic to minimize makespan in proportional parallel flow shops
  publication-title: Int. J. Comput. Inf. Sci.
– volume: vol. 174
  year: 1979
  ident: 10.1016/j.dam.2025.08.004_b16
– volume: 41
  start-page: 3059
  issue: 13
  year: 2003
  ident: 10.1016/j.dam.2025.08.004_b9
  article-title: Parallel flowshop scheduling using Tabu search
  publication-title: Int. J. Prod. Res.
  doi: 10.1080/0020754031000106443
– volume: 734
  start-page: 24
  year: 2018
  ident: 10.1016/j.dam.2025.08.004_b34
  article-title: An approximation scheme for minimizing the makespan of the parallel identical multi-stage flow-shops
  publication-title: Theoret. Comput. Sci.
  doi: 10.1016/j.tcs.2017.09.018
– volume: 281
  start-page: 16
  issue: 1
  year: 2020
  ident: 10.1016/j.dam.2025.08.004_b14
  article-title: A polynomial-time approximation scheme for an arbitrary number of parallel two-stage flow-shops
  publication-title: European J. Oper. Res.
  doi: 10.1016/j.ejor.2019.08.019
– volume: 28
  start-page: 129
  year: 1996
  ident: 10.1016/j.dam.2025.08.004_b23
  article-title: A scheduling problem in glass manufacturing
  publication-title: IIE Trans.
  doi: 10.1080/07408179608966258
– volume: 131
  year: 2020
  ident: 10.1016/j.dam.2025.08.004_b36
  article-title: Coupled task scheduling for heterogeneous multi-robot system of two robot types performing complex-schedule order fulfillment tasks
  publication-title: Robot. Auton. Syst.
  doi: 10.1016/j.robot.2020.103560
– volume: 45
  start-page: 611
  issue: 6
  year: 1994
  ident: 10.1016/j.dam.2025.08.004_b29
  article-title: An overview of scheduling problems arising in satellite communications
  publication-title: J. Oper. Res. Soc.
  doi: 10.1057/jors.1994.99
– volume: 23
  start-page: 665
  issue: 4
  year: 1976
  ident: 10.1016/j.dam.2025.08.004_b18
  article-title: Open shop scheduling to minimize finish time
  publication-title: J. ACM
  doi: 10.1145/321978.321985
– volume: 295
  start-page: 399
  issue: 2
  year: 2021
  ident: 10.1016/j.dam.2025.08.004_b3
  article-title: Four decades of research on the open-shop scheduling problem to minimize the makespan
  publication-title: European J. Oper. Res.
  doi: 10.1016/j.ejor.2021.03.026
– volume: 216
  start-page: 544
  issue: 3
  year: 2012
  ident: 10.1016/j.dam.2025.08.004_b43
  article-title: Approximation algorithms for the parallel flow shop problem
  publication-title: European J. Oper. Res.
  doi: 10.1016/j.ejor.2011.08.007
– volume: 32
  start-page: 687
  issue: 8
  year: 2000
  ident: 10.1016/j.dam.2025.08.004_b35
  article-title: The use of flowlines to simplify routing complexity in two-stage flowshops
  publication-title: Iie Trans.
  doi: 10.1080/07408170008967427
– ident: 10.1016/j.dam.2025.08.004_b12
– volume: 335
  start-page: 185
  issue: 1
  year: 2024
  ident: 10.1016/j.dam.2025.08.004_b17
  article-title: A polynomial-time approximation scheme for an arbitrary number of parallel identical multi-stage flow-shops
  publication-title: Ann. Oper. Res.
  doi: 10.1007/s10479-024-05860-6
– volume: 21
  start-page: 559
  issue: 4
  year: 2019
  ident: 10.1016/j.dam.2025.08.004_b8
  article-title: Practical approaches to chemical tanker scheduling in ports: a case study on the Port of Houston
  publication-title: Marit. Econ. Logist.
  doi: 10.1057/s41278-019-00122-w
– volume: 776
  start-page: 117
  year: 2019
  ident: 10.1016/j.dam.2025.08.004_b40
  article-title: Scheduling two-stage jobs on multiple flowshops
  publication-title: Theoret. Comput. Sci.
  doi: 10.1016/j.tcs.2019.01.017
– volume: 7
  start-page: 33
  issue: 01
  year: 2015
  ident: 10.1016/j.dam.2025.08.004_b5
  article-title: Literature review of open shop scheduling problems
  publication-title: Intell. Inf. Manag.
– volume: 37
  start-page: 668
  issue: 2
  year: 2019
  ident: 10.1016/j.dam.2025.08.004_b13
  article-title: A fully polynomial time approximation scheme for scheduling on parallel identical two-stage openshops
  publication-title: J. Comb. Optim.
  doi: 10.1007/s10878-018-0314-6
– volume: 82
  start-page: 175
  issue: 1
  year: 1998
  ident: 10.1016/j.dam.2025.08.004_b22
  article-title: Approximability of flow shop scheduling
  publication-title: Math. Program.
  doi: 10.1007/BF01585870
– volume: 45
  start-page: 288
  issue: 2
  year: 1997
  ident: 10.1016/j.dam.2025.08.004_b37
  article-title: Short shop schedules
  publication-title: Oper. Res.
  doi: 10.1287/opre.45.2.288
– volume: 786
  start-page: 67
  year: 2019
  ident: 10.1016/j.dam.2025.08.004_b39
  article-title: On scheduling inclined jobs on multiple two-stage flowshops
  publication-title: Theoret. Comput. Sci.
  doi: 10.1016/j.tcs.2018.04.005
– volume: 23
  start-page: 116
  issue: 1
  year: 1976
  ident: 10.1016/j.dam.2025.08.004_b30
  article-title: Algorithms for scheduling independent tasks
  publication-title: J. ACM
  doi: 10.1145/321921.321934
– volume: 40
  start-page: 547
  year: 2020
  ident: 10.1016/j.dam.2025.08.004_b1
  article-title: Multiprocessor open shop problem: literature review and future directions
  publication-title: J. Comb. Optim.
  doi: 10.1007/s10878-020-00591-3
– volume: 806
  start-page: 509
  year: 2020
  ident: 10.1016/j.dam.2025.08.004_b41
  article-title: Improved approximation algorithms for two-stage flowshops scheduling problem
  publication-title: Theoret. Comput. Sci.
  doi: 10.1016/j.tcs.2019.08.028
– volume: 29
  start-page: 973
  issue: 5
  year: 2018
  ident: 10.1016/j.dam.2025.08.004_b44
  article-title: A bi-objective genetic algorithm for intelligent rehabilitation scheduling considering therapy precedence constraints
  publication-title: J. Intell. Manuf.
  doi: 10.1007/s10845-015-1149-y
– volume: 70
  start-page: 379
  issue: 3
  year: 1993
  ident: 10.1016/j.dam.2025.08.004_b10
  article-title: Worst-case analysis of heuristics for open shops with parallel machines
  publication-title: European J. Oper. Res.
  doi: 10.1016/0377-2217(93)90249-M
– volume: 818
  start-page: 74
  year: 2020
  ident: 10.1016/j.dam.2025.08.004_b42
  article-title: On scheduling multiple two-stage flowshops
  publication-title: Theoret. Comput. Sci.
  doi: 10.1016/j.tcs.2018.04.017
– volume: vol. 5
  start-page: 287
  year: 1979
  ident: 10.1016/j.dam.2025.08.004_b20
  article-title: Optimization and approximation in deterministic sequencing and scheduling: a survey
– year: 2022
  ident: 10.1016/j.dam.2025.08.004_b27
  article-title: A book of open shop scheduling
  publication-title: Int. Ser. Oper. Res. Manag. Sci.
– volume: 19
  start-page: 52
  issue: 1
  year: 2017
  ident: 10.1016/j.dam.2025.08.004_b7
  article-title: Strategic idleness and dynamic scheduling in an open-shop service network: Case study and analysis
  publication-title: Manuf. Serv. Oper. Manag.
  doi: 10.1287/msom.2016.0591
– volume: 45
  start-page: 1563
  issue: 9
  year: 1966
  ident: 10.1016/j.dam.2025.08.004_b19
  article-title: Bounds for certain multiprocessing anomalies
  publication-title: Bell Syst. Tech. J.
  doi: 10.1002/j.1538-7305.1966.tb01709.x
– volume: 34
  start-page: 144
  issue: 1
  year: 1987
  ident: 10.1016/j.dam.2025.08.004_b24
  article-title: Using dual approximation algorithms for scheduling problems theoretical and practical results
  publication-title: J. ACM
  doi: 10.1145/7531.7535
– ident: 10.1016/j.dam.2025.08.004_b38
– year: 2022
  ident: 10.1016/j.dam.2025.08.004_b33
  article-title: Complexity and approximation of open shop scheduling to minimize the makespan: A review of models and approaches
  publication-title: Comput. Oper. Res.
  doi: 10.1016/j.cor.2022.105732
SSID ssj0001218
ssj0000186
ssj0006644
Score 2.4351025
Snippet Various new scheduling problems have been arising from real-world applications and spawning new research areas in the scheduling field. We study the parallel...
SourceID crossref
elsevier
SourceType Index Database
Publisher
StartPage 390
SubjectTerms Efficient polynomial-time approximation scheme
Linear programming
Makespan
Parallel multi-stage open shops
Scheduling
Title An efficient polynomial-time approximation scheme for parallel multi-stage open shops
URI https://dx.doi.org/10.1016/j.dam.2025.08.004
Volume 377
WOSCitedRecordID wos001558940100001&url=https%3A%2F%2Fcvtisr.summon.serialssolutions.com%2F%23%21%2Fsearch%3Fho%3Df%26include.ft.matches%3Dt%26l%3Dnull%26q%3D
hasFullText 1
inHoldings 1
isFullTextHit
isPrint
journalDatabaseRights – providerCode: PRVESC
  databaseName: Elsevier SD Freedom Collection Journals 2021
  issn: 0166-218X
  databaseCode: AIEXJ
  dateStart: 20211207
  customDbUrl:
  isFulltext: true
  dateEnd: 99991231
  titleUrlDefault: https://www.sciencedirect.com
  omitProxy: false
  ssIdentifier: ssj0001218
  providerName: Elsevier
– providerCode: PRVESC
  databaseName: Elsevier SD Freedom Collection Journals 2021
  issn: 0166-218X
  databaseCode: AIEXJ
  dateStart: 20220331
  customDbUrl:
  isFulltext: true
  dateEnd: 99991231
  titleUrlDefault: https://www.sciencedirect.com
  omitProxy: false
  ssIdentifier: ssj0001218
  providerName: Elsevier
link http://cvtisr.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwtV1RT9swELZG2QM8TIyBgLHJD3sCRWoTx64fq62MTRuaGEh9i5zEEUElrWiLyr_nLme3WWESm8RLFFlxHN19cj6fz98x9klIa62M8kDnGhYoWsSBxjCH0sZIHasiK2p1_R_q7Kw7GOhfbgd_UpcTUFXVnc_1-EVdDW3gbDw6-w_uXrwUGuAenA5XcDtcn-X4XoVJGmV90BFrMNzjwWMzDLCKPEmIz0s6r3gMK1t7Q6rfKAE-HNohZRgGwBkxmjC28NDVaDxpctgvJUw1wLUXDPbnQvp1WaXeZ_oC-m783xETdUiy4Hx238gForavs9HVrFxuUtXI811dXCKMvfqhD5Y9OjBD8UspA2AVg-YEHLlCLjSFRlQ-1P2NBYU6Hk30FHO4huFRTiCMax1WKmS8op_9G8fEIYHsAX9tt9fYeqhiDVPgeu9bf_C9oTaGUnobPj633I4CWiacSDx9vd8erxMFVz7haYLTIC0XW-yNW23wHqHkLXtlq2222fDXO3bZq_gCL3wFL_wPvHDCCwe8cI8X3sALR7zwGi877PKkf_H5NHC1NoIMGO40kDrP8lybSGqkeCJH5izbBiwWS2XDrABmp6SN0tBKZQp4zGaRSpXKpc5iHe2yVjWq7B7jhe2aTjftWKNSgd10GgKxzDqhEXFUmH125A2UjElSJfG5htcJWDNBayZYHbUt9pnwJkwcJySulwAS_t7t4P-6vWcbSygfstb0dmY_sNfZ3bSc3H50eHkAqdWDrA
linkProvider Elsevier
openUrl ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Ajournal&rft.genre=article&rft.atitle=An+efficient+polynomial-time+approximation+scheme+for+parallel+multi-stage+open+shops&rft.jtitle=Discrete+Applied+Mathematics&rft.au=Dong%2C+Jianming&rft.au=Jin%2C+Ruyan&rft.au=Lin%2C+Guohui&rft.au=Su%2C+Bing&rft.date=2025-12-31&rft.pub=Elsevier+B.V&rft.issn=0166-218X&rft.volume=377&rft.spage=390&rft.epage=401&rft_id=info:doi/10.1016%2Fj.dam.2025.08.004&rft.externalDocID=S0166218X25004500
thumbnail_l http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/lc.gif&issn=0166-218X&client=summon
thumbnail_m http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/mc.gif&issn=0166-218X&client=summon
thumbnail_s http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/sc.gif&issn=0166-218X&client=summon