An FPTAS for two performance measures for the relocation scheduling problem subject to fixed processing sequences

In this paper we consider a resource-constrained scheduling problem on two parallel dedicated machines with given fixed processing sequences of jobs assigned to each one of the machines. The problem is to determine the starting times of all jobs, subject to the resource constraint, in order to minim...

Celý popis

Uloženo v:
Podrobná bibliografie
Vydáno v:Optimization letters Ročník 16; číslo 4; s. 1181 - 1196
Hlavní autoři: Halman, Nir, Vinetz, Uriel
Médium: Journal Article
Jazyk:angličtina
Vydáno: Berlin/Heidelberg Springer Berlin Heidelberg 01.05.2022
Témata:
ISSN:1862-4472, 1862-4480
On-line přístup:Získat plný text
Tagy: Přidat tag
Žádné tagy, Buďte první, kdo vytvoří štítek k tomuto záznamu!
Popis
Shrnutí:In this paper we consider a resource-constrained scheduling problem on two parallel dedicated machines with given fixed processing sequences of jobs assigned to each one of the machines. The problem is to determine the starting times of all jobs, subject to the resource constraint, in order to minimize some given performance measure. Lin et al. (J Sched 19(2):153–163, 2016) showed that the problem is NP-hard in the ordinary sense under the performance measures of weighted total tardiness and weighted number of tardy jobs, and questioned the existence of approximation schemes. In this paper we answer their question in the affirmative by designing fully polynomial time approximation schemes.
ISSN:1862-4472
1862-4480
DOI:10.1007/s11590-021-01772-7